Maryland Statutes
Subtitle 8 - Surface Mining
Section 15-819 - Transfer of Permit

(a)    When the interest of a permittee in any uncompleted mining operation is sold, leased, assigned, or otherwise disposed of, the Department may release the first permittee from all liabilities imposed upon him by this subtitle with reference to the operation and transfer the permit to the successor in interest, if both the permittee and the successor in interest have complied with the requirements of this subtitle and the successor in interest assumes the duties and responsibilities of the first permittee with reference to reclamation of the land according to the authorized mining and reclamation plan and posts suitable bond or other security required by § 15-823 of this subtitle.
    (b)    The successor in interest shall pay a $500 fee on filing a transfer of permit.
    (c)    The Department shall approve and grant the permit transfer as expeditiously as possible but not later than 30 days after the application forms or any supplemental information required are filed with the Department.
    (d)    The Department may deny the permit transfer on finding:
        (1)    That either permittee has an uncorrected violation of the type listed in § 15-810(b)(7) of this subtitle;
        (2)    Failure of the successor permittee to submit an adequate mining and reclamation plan in light of conditions existing at the time of the modification; or
        (3)    Failure of the successor permittee to pay the transfer fee.
    (e)    If the Department denies an application to transfer a permit, the Department shall give the permittee and the successor in interest written notice of:
        (1)    The Department’s determination;
        (2)    Any changes in the application which would make it acceptable; and
        (3)    The right of the permittee and the successor in interest to a hearing at a stated time and place.
    (f)    The date for the hearing may not be less than 15 days nor more than 30 days after the date of the notice unless the parties mutually agree on another date.

Structure Maryland Statutes

Maryland Statutes

Environment

Title 15 - Mines and Mining

Subtitle 8 - Surface Mining

Section 15-801 - Definitions

Section 15-802 - Legislative Intent

Section 15-803 - Regulations

Section 15-804 - Review of Mineral Resources Plans

Section 15-805 - Surface Mined Land Reclamation Fund

Section 15-806 - Surface Mine Inspectors

Section 15-807 - Surface Mining License

Section 15-808 - Surface Mining Permit Generally

Section 15-809 - Review of Application and Accompanying Documents; Notice; Hearing

Section 15-810 - Approval or Denial of Permit

Section 15-811 - Conditions for a Permit

Section 15-812 - Dewatering in Karst Terrain; Legislative Intent; Zones of Dewatering Influence Established; Program Established

Section 15-813 - Permit Conditions for Dewatering a Pit in Karst Terrain

Section 15-814 - Length of Term of Permit

Section 15-815 - Permit Modification

Section 15-816 - Permit Renewal

Section 15-817 - Effective Date of Modification or Renewal

Section 15-818 - New Permit in Lieu of Modification or Renewal

Section 15-819 - Transfer of Permit

Section 15-820 - Departmental Modification of Permit or of Mining and Reclamation Plan

Section 15-821 - Suspension or Revocation of a Permit

Section 15-822 - Mining and Reclamation Plan

Section 15-823 - Performance Bonds or Cash Deposits

Section 15-824 - Release of Bond

Section 15-825 - Forfeiture of Bond

Section 15-826 - Mining After Forfeiture of Bond

Section 15-827 - Annual Mining and Reclamation Reports

Section 15-828 - Inspection and Approval of Reclamation

Section 15-829 - Abandoned or Halted Operations

Section 15-830 - Final Completion Inspection and Report

Section 15-831 - Specifications for Construction Projects

Section 15-832 - Civil Action and Injunction

Section 15-833 - Inapplicability of Subtitle

Section 15-834 - Exemptions