76-7,132. Same; construction management at-risk project delivery procedures; construction manager, selection of; construction services bid, notice requirements. Construction management at-risk project delivery procedures shall be conducted as follows:
(a) The state board shall determine the scope and level of detail required to permit qualified construction manager or general contractors to submit construction management at-risk proposals in accordance with the request for proposals given the nature of the project.
(b) Prior to completion of the construction documents, but as early as during the schematic design phase, the construction manager or general contractor shall be selected. The project design professional may be employed or retained by the institution to assist in the selection process.
(c) The institution shall publish a notice of the request for qualifications and proposals for the required project services at least 15 days prior to the commencement of such requests in the Kansas register in accordance with K.S.A. 75-430a, and amendments thereto, notify all active general contractor industry associations in the state of such request at the same time of the notice and publish in such other appropriate manner as may be determined by the institution.
(d) The state board shall solicit proposals in a three stage qualifications based selection process. Phase I shall be the solicitation of qualifications and prequalifying a minimum of three but no more than five construction managers or general contractors to advance to phase II. Phase II shall be the solicitation of a request for proposal for the project, and phase III shall include an interview with each proposer to present their qualifications and answer questions.
(1) Phase I shall require all proposers to submit a statement of qualifications which shall include, but not be limited to:
(A) Similar project experience;
(B) experience in this type of project delivery system;
(C) references from design professionals and owners from previous projects;
(D) description of the construction manager's or general contractor's project management approach;
(E) financial statements; and
(F) bonding capacity.
Firms submitting a statement of qualifications shall be capable of providing a public works bond in accordance with K.S.A. 60-1111, and amendments thereto, and shall present evidence of such bonding capacity to the procurement committee with their statement of qualifications. If a firm fails to present such evidence, such firm shall be deemed unqualified for selection under this subsection.
(2) The procurement committee shall evaluate the qualifications of all proposers in accordance with the instructions of the request for qualifications. The procurement committee shall prepare a short list containing a minimum of three and maximum of five qualified firms, which have the best and most relevant qualifications to perform the services required of the project, to participate in phase II of the selection process. If three qualified proposers cannot be identified, the selection process shall cease. The procurement committee shall have discretion to disqualify any proposer that, in the procurement committee's opinion, lacks the minimal qualifications required to perform the work.
(3) Phase II of the process shall be conducted as follows:
(A) Prequalified firms selected in phase I shall be given a request for proposal. The request for proposal shall require all proposers to submit a more in depth response including, but not be limited to:
(i) Company overview;
(ii) experience or references, or both, relative to the project under question;
(iii) resumes of proposed project personnel;
(iv) overview of preconstruction services;
(v) overview of construction planning; and
(vi) proposed safety plan.
(B) All proposers shall submit proposed fees, including fees for preconstruction services, fees for general conditions, fees for overhead and profit and fees for self-performed work, if any, directly and only to the secretary of administration. The secretary of administration shall consider and make recommendations to the negotiating committee on the fees. The recommendations by the secretary of administration shall be open for public review. The scores on fees shall not account for more than 25% of the total possible score.
(4) Phase III shall be conducted as follows:
(A) (i) Once all proposals have been submitted, a negotiating committee shall interview all of the proposers, allowing the competing firms to present their proposed team members, qualifications and project plan and to answer questions. Interview scores shall not account for more than 50% of the total possible score.
(ii) A negotiating committee shall be composed of the head of the institution for which the proposed construction project is planned, or a person designated by the head of the institution, and two other persons designated by the head of the institution for which the proposed project is planned.
(B) The negotiating committee shall select the firm providing the best value based on the proposal criteria, weighting factors utilized to emphasize important elements of each project and recommendation of the secretary of administration. All scoring criteria and weighting factors shall be identified by the institution in the request for proposal instructions to proposers. The negotiating committee shall proceed to negotiate with and attempt to enter into a contract with the firm receiving the best total score to serve as the construction manager or general contractor for the project. If the negotiating committee be unable to negotiate a satisfactory contract with the firm scoring the best total score, negotiations with that firm shall be terminated, and the committee shall undertake negotiations with the firm with the next best total score, in accordance with this section.
(C) If the negotiating committee determines that it is not in the best interest of the institution to proceed with the project pursuant to the proposals offered, the negotiating committee shall reject all proposals. If all proposals are rejected, the state board may solicit new proposals using different design criteria, budget constraints or qualifications.
(D) The contract to perform construction management at-risk services for a project shall be prepared by the institution and entered into between the institution and the firm performing such construction management at-risk services. A construction management at-risk contract utilizing a cost plus guaranteed maximum price contract value shall return all savings under the guaranteed maximum price to the institution.
(E) The institution shall publish a construction services bid notice in the Kansas register and in such other appropriate manner for the construction manager or general contractor as may be determined by the institution. Each construction services bid notice shall include the request for bids and other bidding information prepared by the construction manager or general contractor and the institution. The institution may allow the construction manager or general contractor to self-perform construction services provided the construction manager or general contractor submits a bid proposal prior to receipt of all other bids and under the same conditions as all other competing firms. If a firm submitting a bid proposal fails to present such evidence, such firm shall be deemed unqualified for selection under this subsection. At the time for opening the bids, the construction manager or general contractor shall evaluate the bids and shall determine the lowest responsible bidder except in the case of self-performed work for which the institution shall determine the lowest responsible bidder. The construction manager or general contractor shall enter into a contract with each firm performing the construction services for the project and make a public announcement of each firm selected in accordance with this subsection.
History: L. 2009, ch. 86, § 7; L. 2015, ch. 11, § 6; July 1.
Structure Kansas Statutes
Chapter 76 - State Institutions And Agencies; Historical Property
Article 7 - State Educational Institutions; Management And Operation
76-714 Chief executive officers; titles; appointment; compensation.
76-715 Appointment of employees; compensation.
76-715a Conversion of certain employees to the unclassified service.
76-715b Leave time for classified employees of state education institutions, authorization.
76-716 Determination of programs offered and degrees to be granted.
76-717a Report to legislature.
76-717b Entitlement to admission to state educational institutions; requirements.
76-718 Dedication of certain moneys.
76-719a Fellowships and scholarships for graduate students; legislative declaration.
76-722 Holding property and executing trusts.
76-723 Federal funds; application for, receipt, deposit and expenditure.
76-724 Private grants and bequests.
76-725 Administration of state educational institutions; delegation of authority.
76-727 Recruitment of personnel; payment of certain expenses authorized.
76-730 Same; rules and regulations for criteria and guidelines; student residence committees.
76-731 Certain American Indians deemed residents of state for purpose of tuition and fees.
76-733 Same; investment of funds; administrative expenses; credits to subsidiary accounts.
76-734 Same; nonliability of state or agencies thereof.
76-738 Refunds of tuition, fees or charges by institutions under state board of regents.
76-740 Same; reimbursement for certain costs; federal guidelines.
76-742 Student fees for debt service on academic or health facilities, prior referendum required.
76-749 Insurance for study abroad programs, contracts.
76-750 Accident and health insurance, women's intercollegiate athletics.
76-751 Sponsored research at state educational institutions; definition.
76-752 Same; project contracts; authorized expenditures, when; bidding and other exemptions.
76-754 Service clearing funds; definition.
76-755 Same; authorized uses; approval of additional activities; accounting procedures.
76-761 Housing system; creation and operation; rents and fees.
76-761a Student housing; meningitis vaccination.
76-763 Same; housing properties; acquisition of sites and buildings.
76-765 Same; bonds outstanding on project; effect.
76-766 Same; "state education institution" defined.
76-767 Center for innovative school leadership; duties.
76-768 Use of social security number prohibited, when.
76-773 Kansas partnership for faculty of distinction program; definitions.
76-777 University research and development enhancement act; citation of act.
76-780 General powers, duties and functions of state board of regents.
76-782 Research and development facility projects authorized.
76-784 Sales and use tax exemptions, purchases for research and development facility projects.
76-787 Contracts for certain research and development facilities, provisions for prevailing wages.
76-790 Privately-financed buildings; maintenance costs.
76-791 Payment of bonds from contributions qualifying as tax credit, limitation.
76-7,101 Long-term infrastructure maintenance program.
76-7,103 Same; administration of program; reports; building inventory and space utilization.
76-7,104 Same; infrastructure maintenance fund.
76-7,106 Same; transfers of moneys from statewide maintenance and disaster relief fund.
76-7,107 Long-term infrastructure maintenance program; transfers of moneys from state general fund.
76-7,116 Infrastructure finance program.
76-7,118 Same; administration of program; reports.
76-7,119 Same; bonds not a state obligation.
76-7,120 Same; bonds; limitations; loan agreements.
76-7,125 State educational institution project delivery construction procurement act; citation.
76-7,127 Same; projects financed with non-state moneys; exempt from certain statutory requirements.
76-7,128 Same; contracts; bids; duties of state board and institutions.
76-7,129 Same; contracts, change orders.
76-7,130 Same; local building codes, fees, building permits and zoning requirements, exemptions.
76-7,133 Same; rules and regulations.
76-7,137 University engineering initiative act; purpose.
76-7,141 Kan-grow engineering funds, state educational institutions; purposes.
76-7,142 Sales tax exemption, expenditures for engineering initiative facilities.
76-7,143 Liberal construction of act.
76-7,151 Expenditure of state moneys; limitations; remedial courses.