Kansas Statutes
Article 4 - Mined-land Conservation And Reclamation
49-415 Reclamation reports; release of bond, when; hearing; conduct of hearing.

49-415. Reclamation reports; release of bond, when; hearing; conduct of hearing. Within 60 days after the date of expiration of a permit, the operator shall file with the secretary a report stating the exact number of acres of land affected by the operation, the extent of the reclamation already accomplished by it, and such other information as may be required by the secretary. The report shall be accompanied by a copy of the map filed with the original application which shall show any revisions made necessary by result of the operation.
The operator may file a request with the secretary for release of all or part of a bond. The secretary shall prescribe by regulation procedures consistent with the national surface mining control and reclamation act of 1977 (public law 95-87), for public advertisement of such release request, notification of interested property owners and public agencies, inspection and evaluation of requests, corrective action, public hearings, and release of bonds. The secretary may release in whole or in part any bond if satisfied the reclamation covered by the bond has been accomplished as required by this act according to the following schedule:
(1) When the operator completes the backfilling, regrading, and drainage control of a bonded area in accordance with the operator's approved reclamation plan, the release of 60% of the bond for the applicable permit area.
(2) After revegetation has been established on the regraded mined lands in accordance with the approved reclamation plan. When determining the amount of bond to be released after successful revegetation has been established, the department shall retain that amount of bond for the revegetated area which would be sufficient for a third party to cover the cost of reestablishing revegetation for the period required by the national surface mining control and reclamation act of 1977 (public law 95-87). No part of the bond or deposit shall be released under this paragraph so long as the lands to which the release would be applicable are contributing suspended solids to streamflow or run-off outside the permit area in excess of the requirements set by law or until soil productivity for prime farm lands has returned to equivalent levels of yield as nonmined land of the same soil type in the surrounding area under equivalent management practices as determined from a soil survey performed. Where a silt dam is to be retained as a permanent impoundment, the portion of bond may be released under this paragraph as long as provisions for sound future maintenance by the operator or the landowner have been made with the department.
(3) When the operator has completed successfully all surface coal mining and reclamation activities, the remaining portion of the bond shall be released, but not before the expiration of the period specified for operator responsibility. No bond shall be fully released until all reclamation requirements of this act are fully met.
Any person with a valid legal interest which might be adversely affected by release of the bond or the responsible officer or head of any federal, state, or local governmental agency which has jurisdiction by law or special expertise with respect to any environmental, social, or economic impact involved in the operation, or is authorized to develop and enforce environmental standards with respect to such operations shall have the right to file written objections to the proposed release from bond with the secretary within 30 days after the last publication of notice as required by the secretary and specified by rules and regulations adopted by the secretary. If written objections are filed, and a hearing requested, the secretary shall inform all the interested parties of the time and place of the hearing, and hold a public hearing in the locality of the surface coal mining operation proposed for bond release within 30 days of the request for such hearing. The date, time, and location of such public hearings shall be advertised by the department in a newspaper of general circulation in the locality for two consecutive weeks. The secretary shall hold a public hearing in the locality of the surface coal mining operation proposed for bond release within 30 days of the request for such hearing.
For the purpose of such hearing the secretary or hearing officer shall have the authority and is hereby empowered to administer oaths, subpoena witnesses, or written or printed materials, compel the attendance of witnesses, or production of the materials, and take evidence including but not limited to inspections of the land affected and other surface coal mining operations carried on by the applicant in the general vicinity. A verbatim record of each public hearing required by this act shall be made, and a transcript made available on the motion of any party or by order of the secretary.
History: L. 1968, ch. 395, § 15; L. 1978, ch. 208, § 11; L. 1979, ch. 169, § 8; L. 1988, ch. 192, § 20; July 1.

Structure Kansas Statutes

Kansas Statutes

Chapter 49 - Mines And Mining

Article 4 - Mined-land Conservation And Reclamation

49-401 Short title.

49-402 Declaration of policy.

49-402a Jurisdiction and authority vested in department of health and environment; powers, duties and functions conferred; abolition of board and office of executive director; application of documentary references and designations; rules and regulati...

49-402b Appropriations, unexpended balances transferred, use; officers and employees, liability for accrued compensation assumed by department of health and environment.

49-402c Property and records transferred; resolution of conflicts by governor.

49-402d Rights saved in legal actions and proceedings.

49-402e Officers and employees transferred; civil service status; benefits and rights retained.

49-403 Definitions.

49-404 Employment of inspectors and other personnel; contracts for technical services authorized; financial interest in coal mining operation prohibited; penalties for violation of prohibition; rules and regulations for enforcement; reports to congre...

49-405 Powers and authority of secretary.

49-405a Training, examination and certification of certain persons responsible for blasting or use of explosives; rules and regulations requiring.

49-405b Area designated as unsuitable for surface coal mining operations, when; petition to have area so designated or designation terminated; hearing; duties of secretary.

49-405c Civil penalty for violation of permit condition or provision of act; determination of amount of penalty; hearing; criminal penalty for violations; civil penalty for failure to correct a violation for which a citation has been issued; right to...

49-405d Inspections, when; reports; signs, where, required information; violations; public records.

49-406 Permit to engage in surface mining; compliance with federal act required; annual statement of coal mined; application for permit, contents; notice of application for permit, publication; map and plan to accompany application; disapproval of ap...

49-407 Permit to engage in surface mining; approval, modification or denial; determination and order of secretary, contents; applicant to file schedule listing notices of violation; prime farmland area, effect; informal conference; notice and hearing...

49-408 Reclamation of land; regulations of secretary; public waters, extent.

49-409 Revegetation of affected areas.

49-410 Amendment of permit, application; requirements; limitation on transfer, assignment or sale of rights granted under permit; revision or modification of permit.

49-411 Commencement of reclamation, when; grading.

49-413 Planting report; inspection and evaluation of vegetative cover.

49-415 Reclamation reports; release of bond, when; hearing; conduct of hearing.

49-416 Effect of revocation of permit or forfeiture of bond upon future permits.

49-416a Review of notice or order; investigation and public hearing; order vacating, affirming, modifying or terminating notice or order; show cause order to suspend or revoke permit, hearing; assessment of costs.

49-417 Reclamation by secretary; use of authorized funds; authority to contract; competitive bids; posting of bond or cash deposit by contractor; release of operator's bond, when.

49-418 Effect on existing laws.

49-420 Mined-land conservation and reclamation fee fund and mined-land reclamation fund; administrative expenses.

49-421a Penalty for interference with performance of duties of department or its employees or agents.

49-422a Judicial review.

49-423 Savings clause.

49-425 Interests in water resources not affected; replacement of water supply.

49-426 Civil action to compel compliance with act; limitations; award of costs of litigation; rights to seek other relief not restricted; action for damages for injuries.

49-427 Coal exploration operations; exploration regulations; trade secrets or privileged commercial or financial information confidential; limitations on amount of coal removed under exploration permit.

49-428 Reclamation of land having abandoned mines; plans and programs developed by secretary; abandoned mined-land fund created; priorities in development of plans and programs; abandoned mines eligible for inclusion; application to secretary of inte...

49-429 Application of act to underground coal mining.

49-430 Supplemental provisions.

49-431 Act not applicable to extraction of coal in certain circumstances.

49-432 Authority of secretary and department personnel to enter property for certain purposes; entry construed as exercise of police power; studies, exploratory work.