§269E-9 Identification of subsurface installations by operator. (a) Any operator who receives timely notification from the center of any proposed excavation work pursuant to section 269E-7(b) shall within five working days of that notification or before the start of the excavation work, whichever is later, or at a later time mutually agreeable to the operator and the excavator:
(1) Advise the excavator that the operator does not operate any subsurface installations that may be affected by the excavation;
(2) Advise the excavator of the approximate location of the operator's subsurface installations that may be affected by the excavation to the extent and degree of accuracy that the information is available in the records of the operator;
(3) Make available to the excavator, for inspection and copying at the excavator's expense, information in that specific operator's or agency's records on the approximate location of that specific operator's or agency's subsurface installations that may be affected by the excavation to the extent and degree of accuracy that the information is available in that specific operator's or agency's records; or
(4) Locate and field mark in conformance with the American Public Works Association Uniform Color Code the approximate location and the number of subsurface installations that may be affected by the excavation to the extent and degree of accuracy that the information is available as determined through the use of standard locating techniques or based on the records of the operator.
The operator shall promptly notify the center when the operator has fulfilled the requirements of this section. After receiving this notification from all affected operators, the center shall promptly provide notice to the excavator that all affected operators have fulfilled the requirements of this section.
(b) The excavator shall notify the center of any operator's failure to comply with this section and of the applicable inquiry identification number. [L 2004, c 141, pt of §1, §7; am L 2009, c 72, §3]
Structure Hawaii Revised Statutes
Title 15. Transportation and Utilities
269E. One Call Center; Advance Warning to Excavators
269E-3 General duties and powers of the commission.
269E-4 One call center advisory committee.
269E-5 One call center established.
269E-6 One call center financing.
269E-7 Notification of excavation; inquiry identification number.
269E-8 Marking of excavation site.
269E-9 Identification of subsurface installations by operator.
269E-10 Commencement of excavation.
269E-11 Remarking of operator's subsurface installation.
269E-12 Excavation procedures.