Click to view
Provided, however, that the failure to correctly complete any of the blank spaces in the above form shall not invalidate said form so long as the subject matter of said release may reasonably be determined.
Click to view
Provided, however, that the failure to correctly complete any of the blank spaces in the above form shall not invalidate said form so long as the subject matter of said release may reasonably be determined.
Click to view
“ WAIVER AND RELEASE OF LIENAND PAYMENT BOND RIGHTSUPON INTERIM PAYMENT STATE OF GEORGIA COUNTY OF THE UNDERSIGNED MECHANIC AND/OR MATERIALMAN HAS BEEN EMPLOYED BY (NAME OF CONTRACTOR) TO FURNISH (DESCRIBE MATERIALS AND/OR LABOR) FOR THE CONSTRUCTION OF IMPROVEMENTS KNOWN AS (TITLE OF THE PROJECT OR BUILDING) WHICH IS LOCATED IN THE CITY OF , COUNTY OF , AND IS OWNED BY (NAME OF OWNER) AND MORE PARTICULARLY DESCRIBED AS FOLLOWS: (DESCRIBE THE PROPERTY UPON WHICH THE IMPROVEMENTS WERE MADE BY USING EITHER A METES AND BOUNDS DESCRIPTION, THE LAND LOT DISTRICT, BLOCK AND LOT NUMBER, OR STREET ADDRESS OF THE PROJECT.) UPON THE RECEIPT OF THE SUM OF $, THE MECHANIC AND/OR MATERIALMAN WAIVES AND RELEASES ANY AND ALL LIENS OR CLAIMS OF LIENS IT HAS UPON THE FOREGOING DESCRIBED PROPERTY OR ANY RIGHTS AGAINST ANY LABOR AND/OR MATERIAL BOND THROUGH THE DATE OF (DATE) AND EXCEPTING THOSE RIGHTS AND LIENS THAT THE MECHANIC AND/OR MATERIALMAN MIGHT HAVE IN ANY RETAINED AMOUNTS, ON ACCOUNT OF LABOR OR MATERIALS, OR BOTH, FURNISHED BY THE UNDERSIGNED TO OR ON ACCOUNT OF SAID CONTRACTOR FOR SAID BUILDING OR PREMISES. GIVEN UNDER HAND AND SEAL THIS DAY OF , . (SEAL) (WITNESS) (ADDRESS) ” NOTICE: WHEN YOU EXECUTE AND SUBMIT THIS DOCUMENT, YOU SHALL BE CONCLUSIVELY DEEMED TO HAVE WAIVED AND RELEASED ANY AND ALL LIENS AND CLAIMS OF LIENS UPON THE FOREGOING DESCRIBED PROPERTY AND ANY RIGHTS REGARDING ANY LABOR OR MATERIAL BOND REGARDING THE SAID PROPERTY TO THE EXTENT (AND ONLY TO THE EXTENT) SET FORTH ABOVE, EVEN IF YOU HAVE NOT ACTUALLY RECEIVED SUCH PAYMENT, 90 DAYS AFTER THE DATE STATED ABOVE UNLESS YOU FILE AN AFFIDAVIT OF NONPAYMENT PRIOR TO THE EXPIRATION OF SUCH 90 DAY PERIOD. THE FAILURE TO INCLUDE THIS NOTICE LANGUAGE ON THE FORM SHALL RENDER THE FORM UNENFORCEABLE AND INVALID AS A WAIVER AND RELEASE UNDER . O.C.G.A. § 44-14-366
“ WAIVER AND RELEASE OF LIENAND PAYMENT BOND RIGHTS UPON FINAL PAYMENT STATE OF GEORGIA COUNTY OF THE UNDERSIGNED MECHANIC AND/OR MATERIALMAN HAS BEEN EMPLOYED BY (NAME OF CONTRACTOR) TO FURNISH (DESCRIBE MATERIALS AND/OR LABOR) FOR THE CONSTRUCTION OF IMPROVEMENTS KNOWN AS (TITLE OF THE PROJECT OR BUILDING) WHICH IS LOCATED IN THE CITY OF , COUNTY OF , AND IS OWNED BY (NAME OF OWNER) AND MORE PARTICULARLY DESCRIBED AS FOLLOWS: (DESCRIBE THE PROPERTY UPON WHICH THE IMPROVEMENTS WERE MADE BY USING EITHER A METES AND BOUNDS DESCRIPTION, THE LAND LOT DISTRICT, BLOCK AND LOT NUMBER, OR STREET ADDRESS OF THE PROJECT.) UPON THE RECEIPT OF THE SUM OF $ , THE MECHANIC AND/OR MATERIALMAN WAIVES AND RELEASES ANY AND ALL LIENS OR CLAIMS OF LIENS IT HAS UPON THE FOREGOING DESCRIBED PROPERTY OR ANY RIGHTS AGAINST ANY LABOR AND/OR MATERIAL BOND ON ACCOUNT OF LABOR OR MATERIALS, OR BOTH, FURNISHED BY THE UNDERSIGNED TO OR ON ACCOUNT OF SAID CONTRACTOR FOR SAID PROPERTY. GIVEN UNDER HAND AND SEAL THIS DAY OF , . (SEAL) (WITNESS) (ADDRESS) ” NOTICE: WHEN YOU EXECUTE AND SUBMIT THIS DOCUMENT, YOU SHALL BE CONCLUSIVELY DEEMED TO HAVE WAIVED AND RELEASED ANY AND ALL LIENS AND CLAIMS OF LIENS UPON THE FOREGOING DESCRIBED PROPERTY AND ANY RIGHTS REGARDING ANY LABOR OR MATERIAL BOND REGARDING THE SAID PROPERTY TO THE EXTENT (AND ONLY TO THE EXTENT) SET FORTH ABOVE, EVEN IF YOU HAVE NOT ACTUALLY RECEIVED SUCH PAYMENT, 90 DAYS AFTER THE DATE STATED ABOVE UNLESS YOU FILE AN AFFIDAVIT OF NONPAYMENT PRIOR TO THE EXPIRATION OF SUCH 90 DAY PERIOD. THE FAILURE TO INCLUDE THIS NOTICE LANGUAGE ON THE FORM SHALL RENDER THE FORM UNENFORCEABLE AND INVALID AS A WAIVER AND RELEASE UNDER . O.C.G.A. § 44-14-366
“ AFFIDAVIT OF NONPAYMENT UNDER O.C.G.A. § 44-14-366 STATE OF GEORGIA COUNTY OF THE UNDERSIGNED MECHANIC AND/OR MATERIALMAN HAS BEEN EMPLOYED BY (NAME OF CONTRACTOR) TO FURNISH (DESCRIBE MATERIALS AND/OR LABOR) FOR THE CONSTRUCTION OF IMPROVEMENTS KNOWN AS (TITLE OF THE PROJECT OR BUILDING) WHICH IS LOCATED IN THE CITY OF , COUNTY OF , AND IS OWNED BY (NAME OF OWNER) AND MORE PARTICULARLY DESCRIBED AS FOLLOWS: (DESCRIBE THE PROPERTY UPON WHICH THE IMPROVEMENTS WERE MADE BY USING EITHER A METES AND BOUNDS DESCRIPTION, THE LAND LOT DISTRICT, BLOCK AND LOT NUMBER, OR STREET ADDRESS OF THE PROJECT.) PURSUANT TO THE UNDERSIGNED EXECUTED A LIEN WAIVER AND RELEASE WITH RESPECT TO THIS PROPERTY DATED , . THE AMOUNT SET FORTH IN SAID WAIVER AND RELEASE ($) HAS NOT BEEN PAID IN FULL AND $ OF THE AMOUNT SET FORTH IN SAID WAIVER AND RELEASE REMAINS UNPAID, AND THE UNDERSIGNED HEREBY GIVES NOTICE OF SUCH NONPAYMENT. O.C.G.A. § 44-14-366 THE ABOVE FACTS ARE SWORN TRUE AND CORRECT BY THE UNDERSIGNED, THIS DAY OF , . (SEAL) CLAIMANT’S SIGNATURE SWORN TO AND EXECUTED IN THE PRESENCE OF: WITNESS NOTARY PUBLIC WITHIN SEVEN DAYS OF FILING THIS AFFIDAVIT OF NONPAYMENT, THE FILING PARTY SHALL SEND A COPY OF THE AFFIDAVIT BY REGISTERED OR CERTIFIED MAIL OR STATUTORY OVERNIGHT DELIVERY TO THE OWNER OF THE PROPERTY. IF THE FILING PARTY IS NOT IN PRIVITY OF CONTRACT WITH THE PROPERTY OWNER AND A NOTICE OF COMMENCEMENT IS FILED FOR THE IMPROVEMENT ON THE PROPERTY FOR WHICH THE FILING PARTY’S LABOR, SERVICES, OR MATERIALS WERE FURNISHED, A COPY OF THE AFFIDAVIT SHALL BE SENT TO THE CONTRACTOR AT THE ADDRESS SHOWN ON THE NOTICE OF COMMENCEMENT. WHENEVER THE OWNER OF THE PROPERTY IS AN ENTITY ON FILE WITH THE SECRETARY OF STATE’S CORPORATIONS DIVISION, SENDING A COPY OF THE AFFIDAVIT TO THE COMPANY’S ADDRESS OR THE REGISTERED AGENT’S ADDRESS ON FILE WITH THE SECRETARY OF STATE SHALL BE DEEMED SUFFICIENT.”
History. Code 1981, § 44-14-366 , enacted by Ga. L. 1991, p. 915, § 3; Ga. L. 1999, p. 81, § 44; Ga. L. 2008, p. 1063, § 5/SB 374; Ga. L. 2012, p. 775, § 44/HB 942; Ga. L. 2020, p. 733, § 1/SB 315; Ga. L. 2021, p. 446, § 1/SB 143.
The 2008 amendment, effective March 31, 2009, rewrote this Code section.
The 2012 amendment, effective May 1, 2012, part of an Act to revise, modernize, and correct the Code, revised punctuation in subparagraph (f)(2)(C).
The 2020 amendment, effective January 1, 2021, rewrote this Code section.
The 2021 amendment, effective July 1, 2021, substituted “AFFIDAVIT” for “LIEN” in the middle of the last sentence of the form in paragraph (g)(2).
Law reviews.
For note on 1991 enactment of this Code section, see 8 Ga. St. U.L. Rev. 166 (1992).
For annual survey of construction law, see 57 Mercer L. Rev. 79 (2005).
For survey article on construction law, see 60 Mercer L. Rev. 59 (2008).
Structure Georgia Code
Chapter 14 - Mortgages, Conveyances to Secure Debt, and Liens
Part 3 - Mechanics and Materialmen
§ 44-14-361. Creation of Liens; Property to Which Lien Attaches; Items to Be Included in Lien
§ 44-14-361.2. Dissolution of Lien
§ 44-14-361.4. Cancellation or Expiration of Preliminary Notice; Demand for Filing of Claim of Lien
§ 44-14-361.5. Liens of Persons Without Privity of Contract
§ 44-14-362. Cancellation of Preliminary Notice Upon Final Payment; Form of Cancellation
§ 44-14-367. Notice; Required Statement