(a)(1) The Commissioner of Energy and Environmental Protection, in consultation with the procurement manager identified in subsection (l) of section 16-2, the Office of Consumer Counsel and the Attorney General, may, in coordination with other states in the control area of the regional independent system operator, as defined in section 16-1, in coordination with states in a neighboring control area or on behalf of Connecticut alone, solicit proposals, in one solicitation or multiple solicitations, from providers of energy derived from offshore wind facilities that are Class I renewable energy sources, as defined in section 16-1, and any associated transmission, provided the commissioner shall initiate a solicitation not later than fourteen days after the effective date of this section for projects that have a total nameplate capacity rating of up to two thousand megawatts in the aggregate. Any such solicitation or solicitations issued pursuant to this section on and after January 1, 2020, shall be for quantities of energy and within the timing and schedule determined by the commissioner, and may be informed by the Integrated Resources Plan prepared on or before January 1, 2020, pursuant to subsections (b) and (j) of section 16a-3a, provided such schedule shall provide for the solicitation of resources with a nameplate capacity rating of two thousand megawatts in the aggregate by December 31, 2030.
(2) In developing any solicitations pursuant to this section, the commissioner shall include requirements for contract commitments in selected bids that (A) require payment of not less than the prevailing wage, as described in section 31-53, for laborers, workmen and mechanics performing construction activities within the United States with respect to the project, and (B) require selected bidders to engage in a good faith negotiation of a project labor agreement. Any solicitation issued pursuant to this section shall specify the minimum terms that such project labor agreements shall address.
(3) (A) In responding to any solicitations issued pursuant to this section, a bidder shall include an environmental and fisheries mitigation plan for the construction and operation of such offshore wind facilities, provided such plan shall include, but not be limited to, an explicit description of the best management practices the bidder will employ that are informed by the latest science at the time the proposal is made that will avoid, minimize and mitigate any impacts to wildlife, natural resources, ecosystems and traditional or existing water-dependent uses, including, but not limited to, commercial fishing.
(B) In responding to any solicitations issued pursuant to this section, a bidder may include such bidder's plans for the use of skilled labor, including, but not limited to, for any construction and manufacturing components of the proposal including any outreach, hiring and referral systems, or any combination thereof, that are affiliated with an apprenticeship training program registered with the Labor Department pursuant to section 31-22r.
(C) In responding to any solicitations issued pursuant to this section in calendar year 2019, each bidder shall submit at least one proposal for resources eligible pursuant to this section with a nameplate capacity rating of four hundred megawatts. The commissioner may not consider or select any proposals from a bidder that does not submit at least one proposal for resources with a nameplate capacity of four hundred megawatts for any solicitation issued pursuant to this section in calendar year 2019.
(4) For each solicitation issued pursuant to this section, the commissioner shall establish a commission on environmental standards to provide input on best practices for avoiding, minimizing and mitigating any impacts to wildlife, natural resources, ecosystems and traditional or existing water-dependent uses, including, but not limited to, commercial fishing, during the construction and operation of facilities eligible pursuant to this section.
(b) In making any selection of such proposals, the commissioner shall consider factors, including, but not limited to, (1) whether the proposal is in the best interest of ratepayers, including, but not limited to, the delivered price of such sources, (2) whether the proposal promotes electric distribution system reliability, including during winter peak demand, (3) any positive impacts on the state's economic development, (4) whether the proposal is consistent with the requirements to reduce greenhouse gas emissions in accordance with section 22a-200a, (5) whether the proposal is consistent with the policy goals outlined in the Comprehensive Energy Strategy adopted pursuant to section 16a-3d and the Integrated Resources Plan adopted pursuant to section 16a-3a, (6) whether the proposal is consistent with the goals and policies set forth in sections 22a-92 and 25-157t, and (7) whether the proposal uses practices to avoid, minimize and mitigate impacts to wildlife, natural resources, ecosystems and traditional or existing water-dependent uses, including, but not limited to, commercial fishing. In considering whether a proposal has any positive impacts on the state's economic development, the commissioner shall consult with the Commissioner of Economic and Community Development. The commissioner may select proposals from such resources that have a total nameplate capacity rating of not more than two thousand megawatts in the aggregate.
(c) The commissioner may direct the electric distribution companies to enter into power purchase agreements for energy, capacity, any transmission associated with such energy derived from offshore wind facilities that are Class I renewable energy sources as defined in section 16-1 and environmental attributes, or any combination thereof, for periods of not more than twenty years on behalf of all customers of the state's electric distribution companies. Certificates issued by the New England Power Pool Generation Information System for any Class I renewable energy sources procured by an electric distribution company pursuant to this section may be: (1) Sold into the New England Power Pool Generation Information System renewable energy credit market to be used by any electric supplier or electric distribution company to meet the requirements of section 16-245a, provided the revenues from such sale are credited to electric distribution company customers as described in this section; or (2) retained by the electric distribution company to meet the requirements of section 16-245a. In considering whether to sell or retain such certificates, the company shall select the option that is in the best interest of such company's ratepayers.
(d) Any agreement entered into pursuant to this section shall be subject to review and approval by the Public Utilities Regulatory Authority, which review shall be completed not later than (1) ninety days after the date on which such agreement is filed with the authority for any solicitation issued pursuant to this section in calendar year 2019, and (2) one hundred twenty days for any solicitation issued pursuant to this section on and after January 1, 2020. The authority shall approve agreements that it determines (A) provide for the delivery of adequate and reliable products and services, for which there is a clear public need, at a just and reasonable price, (B) are prudent and cost effective, and (C) are between an electric distribution company and a respondent to the solicitation that has the technical, financial and managerial capabilities to perform pursuant to such agreement. The net costs of any such agreement, including costs incurred by the electric distribution companies under the agreement and reasonable costs incurred by the electric distribution companies in connection with the agreement, shall be recovered through a fully reconciling component of electric rates for all customers of electric distribution companies. Any net revenues from the sale of products purchased in accordance with long-term contracts entered into pursuant to this section shall be credited to customers through the same fully reconciling rate component for all customers of the contracting electric distribution company. The commissioner may hire consultants with expertise in quantitative modeling of electric and gas markets to assist in implementing this section, including, but not limited to, the evaluation of proposals submitted pursuant to this section. All reasonable costs associated with the commissioner's solicitation and review of proposals pursuant to this section shall be recoverable through the same fully reconciling rate component for all customers of the electric distribution companies.
(P.A. 19-71, S. 1; P.A. 21-141, S. 11.)
History: P.A. 19-71 effective June 7, 2019; P.A. 21-141 replaced “Connecticut State Apprenticeship Council established pursuant to section 31-22n” with “Labor Department pursuant to section 31-22r”.
Structure Connecticut General Statutes
Title 16a - Planning and Energy Policy
Section 16a-1. - Legislative findings and purpose.
Section 16a-3. - Connecticut Energy Advisory Board.
Section 16a-3a. - Integrated Resources Plan re energy resource procurement.
Section 16a-3b. - Implementation of the Integrated Resources Plan.
Section 16a-3c. - Electric distribution companies' plans to build electric generation facilities.
Section 16a-3d. - Comprehensive Energy Strategy.
Section 16a-3e. - Requirements of the Integrated Resources Plan.
Section 16a-3f. - Solicitation re Class I renewable energy sources.
Section 16a-3g. - Solicitation re Class I renewable energy sources or large-scale hydropower.
Section 16a-3k. - Definitions.
Section 16a-3o. - Study of the value of distributed energy resources.
Section 16a-3p. - Solicitation re energy derived from anaerobic digestion.
Section 16a-4. - Office of Policy and Management. Staff. Regulations.
Section 16a-4a. - Office of Policy and Management. Duties and powers.
Section 16a-4b. - Municipalities may petition for redesignation of planning region. Procedure.
Section 16a-5. - Secretary's investigatory and subpoena powers.
Section 16a-6. - Cooperation of other state agencies. License for sale of gasoline.
Section 16a-7. - Annual report and recommendations by board.
Section 16a-7a. - Annual comprehensive energy plan.
Section 16a-7b. - Condemnation or restriction of operation of energy facility by municipality.
Section 16a-8. - Programs to foster cooperative effort.
Section 16a-9. - Energy emergency plan. Amendments.
Section 16a-10. - Joint legislative committee established.
Section 16a-12. - Energy emergency not covered by state plan. Review and disapproval. Termination.
Section 16a-13d. - Study on establishing a reserve of energy resources.
Section 16a-14a. - Grant program for businesses involved in energy-related products and services.
Section 16a-14b. - Testing programs for energy-related products. Regulations.
Section 16a-14e. - Purchasing pool for purchase of electricity.
Section 16a-16. - Enforcement; injunctions, damages. Remedies not exclusive.