A. As used in this chapter:
"Abandoned" means no longer in service and physically disconnected from a portion of the underground utility line that is in use for storage or conveyance of service.
"Commission" means the State Corporation Commission.
"Contract locator" means any person contracted by an operator specifically to determine the approximate horizontal location of the operator's utility lines that may exist within the area specified by a notice served on a notification center.
"Damage" means any impact upon or removal of support from an underground facility as a result of excavation or demolition which according to the operating practices of the operator would necessitate the repair of such facility.
"Demolish" or "demolition" means any operation by which a structure or mass of material is wrecked, razed, rendered, moved, or removed by means of any tools, equipment, or discharge of explosives which could damage underground utility lines.
"Designer" means any licensed professional designated by the project owner who designs government projects, commercial projects, residential projects consisting of 25 or more units, or industrial projects, which projects require the approval of governmental or regulatory authorities having jurisdiction over the project area.
"Emergency" means a sudden or unexpected occurrence involving a clear and imminent danger, demanding immediate action to prevent or mitigate loss of, or damage to, life, health, property, or essential public services.
"Excavate" or "excavation" means any operation in which earth, rock, or other material in the ground is moved, removed, or otherwise displaced by means of any tools, equipment, or explosives and includes, without limitation, grading, trenching, digging, ditching, dredging, drilling, augering, tunneling, scraping, cable or pipe plowing and driving, wrecking, razing, rendering, moving, or removing any structure or mass of material. "Excavate" or "excavation" shall not include installation of a sign that consists of metal, plastic, or wooden poles placed in the ground by hand or by foot without the use of tools or equipment.
"Extraordinary circumstances" means floods, snow, ice storms, tornadoes, earthquakes, or other natural disasters.
"Hand digging" means any excavation involving nonmechanized tools or equipment. Hand digging includes, but is not limited to, digging with shovels, picks, and manual post hole diggers, vacuum excavation or soft digging.
"Notification center" means an organization whose membership is open to all operators of underground facilities located within the notification center's designated service area, which maintains a data base, provided by its member operators, that includes the geographic areas in which its member operators desire transmissions of notices of proposed excavation, and which has the capability to transmit, within one hour of receipt, notices of proposed excavation to member operators by teletype, telecopy, personal computer, or telephone.
"Notify," "notice" or "notification" means the completed delivery of information to the person to be notified, and the receipt of same by such person in accordance with this chapter. The delivery of information includes, but is not limited to, the use of any electronic or technological means of data transfer.
"Operator" means any person who owns, furnishes or transports materials or services by means of a utility line.
"Person" means any individual, operator, firm, joint venture, partnership, corporation, association, municipality, or other political subdivision, governmental unit, department or agency, and includes any trustee, receiver, assignee, or personal representative thereof.
"Private sewer lateral" means a privately owned, legally authorized utility line that transports wastewater from one or more buildings to a sewer system utility line owned by a sewer system operator.
"Private water lateral" means a privately owned, legally authorized utility line that supplies water from a water system utility line owned by a water system operator to one or more buildings or properties.
"Sewer system" means a system of utility lines used for conveying wastewater, and includes sewer system laterals but does not include private sewer laterals.
"Sewer system lateral" means a lateral utility line located in the public right-of-way or public sewer easement, owned by a sewer system operator, and used to transport wastewater to the operator's main sewer line.
"Sewer system operator" means an operator of a sewer system.
"Soft digging" means any excavation using tools or equipment that utilize air or water pressure as the direct means to break up soil or earth for removal by vacuum excavation.
"Special project notice" means a valid notice to the notification center by an excavator covering a specific, unique or long-term project.
"Utility line" means any item of public or private property which is buried or placed below ground or submerged for use in connection with the storage or conveyance of water, sewage, telecommunications, electric energy, cable television, oil, petroleum products, gas, or other substances, and includes but is not limited to pipes, sewers, combination storm/sanitary sewer systems, conduits, cables, valves, lines, wires, manholes, attachments, and those portions of poles below ground. The term "sewage" as used herein does not include any gravity storm drainage systems. Except for any publicly owned gravity sewer system within a county which has adopted the urban county executive form of government, the term "utility line" does not include any gravity sewer system or any combination gravity storm/sanitary sewer system within any counties, cities, towns or political subdivisions constructed or replaced prior to January 1, 1995. No excavator shall be held liable for the cost to repair damage to any such systems constructed or replaced prior to January 1, 1995, unless such systems are located in accordance with § 56-265.19.
"Water system" means a system of utility lines used for supplying water, and does not include private water laterals.
"Water system operator" means an operator of a water system.
"Willful" means an act done intentionally, knowingly, and purposely, without justifiable excuse, as distinguished from an act done carelessly, thoughtlessly, heedlessly or inadvertently.
"Working day" means every day, except Saturdays, Sundays, and legal state and national holidays.
B. Unless otherwise specified, all time periods used in this chapter shall be calculated from the time of the original notification to the notification center as provided in § 56-265.17. In addition, all time periods exclude Saturdays, Sundays, and legal state and national holidays.
1979, c. 291; 1980, cc. 696, 710; 1992, c. 192; 1994, c. 890; 1996, c. 79; 2002, c. 841; 2010, cc. 205, 777, 832.
Structure Code of Virginia
Title 56 - Public Service Companies
Chapter 10.3 - Underground Utility Damage Prevention Act
§ 56-265.15. Definitions; calculation of time periods
§ 56-265.15:1. Exemptions; routine maintenance
§ 56-265.16:1. Operators to join notification centers; certification
§ 56-265.17:1. Notification and procedures for designers
§ 56-265.17:2. Procedures for project owners
§ 56-265.17:3. Procedures for operators in response to a designer notice
§ 56-265.18. Notification requirements
§ 56-265.19. Duties of operator; regulations
§ 56-265.19:1. Private sewer laterals and sewer system laterals
§ 56-265.20:1. Locating nonmetallic underground utility lines
§ 56-265.22:1. Meetings between excavators and operators
§ 56-265.24. Duties of excavator
§ 56-265.25. Liability of operator and excavator; penalties
§ 56-265.26:1. Utility line depth requirement
§ 56-265.28. Sovereign immunity
§ 56-265.29. Other similar laws
§ 56-265.30. Authority of the State Corporation Commission