Section 39-2-5 - Return of Proposal Guaranties to Bidders Generally; Disposition of Proposal Guaranty When Award Not Made Within 30 Days of Opening of Proposals.

All bid guaranties, except those of the three lowest bona fide bidders, shall be returned immediately after bids have been checked, tabulated, and the relation of the bids established. The bid guaranties of the three lowest bidders shall be returned as soon as the contract bonds and the contract of the successful bidder have been properly executed and approved. When the award is deferred for a period of time longer than 15 days after the opening of the bids, all bid guaranties, except those of the potentially successful bidders, shall be returned. If no award is made within 30 days after the opening of the bids, or such other time as specified in the bid documents, all bids shall be rejected and all guaranties returned, except for any potentially successful bidder that agrees in writing to a stipulated extension in time for consideration of its bid, in which case the awarding authority may permit the potentially successful bidder to substitute a satisfactory bidder's bond for the cashier's check submitted with its bid as a bid guaranty.

Structure Code of Alabama

Code of Alabama

Title 39 - Public Works.

Chapter 2 - Letting, Execution, and Administration of Public Improvements Contracts by State Agencies Generally.

Section 39-2-1 - Definitions.

Section 39-2-2 - Advertisement for and Opening of Sealed Bids for Public Works Contracts; Violations; Exclusions; Emergency Actions; Sole Source Specification.

Section 39-2-3 - Fees to Be Paid Department of Transportation for Proposals, Plans, and Specifications; Deposit for Bid Documents; Furnishing of Plans and Specifications to Building Exchanges, Etc.

Section 39-2-4 - Filing of Guaranties by Bidders; Prequalification Procedures and Criteria; Responsibility of Prequalified Bidders; Revocation of Prequalification; Rejection of Bidder.

Section 39-2-5 - Return of Proposal Guaranties to Bidders Generally; Disposition of Proposal Guaranty When Award Not Made Within 30 Days of Opening of Proposals.

Section 39-2-6 - Award of Contract; Powers of Awarding Authority; Availability of Plans, etc.; Disqualifying Activities; Life Cycle Costs.

Section 39-2-7 - Effect of Errors and Discrepancies of Prices in Bids.

Section 39-2-8 - Execution of Contracts and Furnishing of Performance Bonds, etc., Generally by Bidders Awarded Contracts.

Section 39-2-9 - Approval of Bonds, etc., and Completion of Execution of Contracts by Awarding Authorities.

Section 39-2-10 - Issuance of Proceed Orders by Awarding Authorities, Etc.

Section 39-2-11 - Proceedings Upon Failure of Successful Bidders to Execute Contracts and Furnish Bonds, etc.; Death of a Low Bidder; Effect of Failure of Awarding Authorities to Complete Execution of Contracts and Issue Proceed Orders; Withdrawal of...

Section 39-2-12 - Partial and Final Payments of Contractors by Awarding Authorities.

Section 39-2-13 - Promulgation of Rules and Regulations by Awarding Authorities.

Section 39-2-14 - Registration of Out-of-State Contractors Required; Deposit; Surety Bond.