(2) The period for commencement of construction may be extended once but not longer than two additional years, and the period for the completion of construction carried on in good faith and with reasonable diligence may be extended by the commission when not incompatible with the public interests.
(3) If the licensee does not commence actual construction of the project works or of any specified part of the project works, within the time prescribed in the license or as extended by the commission, then, after due notice given, the license shall, as to the project works or part of the project works, be terminated upon written order of the commission. [Amended by 1985 c.673 §155]
Structure 2021 Oregon Revised Statutes
Volume : 15 - Water Resources, Agriculture and Food
Chapter 543 - Hydroelectric Projects
Section 543.010 - Definitions for ORS 543.010 to 543.610.
Section 543.012 - Applicability of chapter to reauthorization of existing hydroelectric project.
Section 543.013 - Applicability of chapter and ORS chapter 543A to ocean renewable energy facility.
Section 543.055 - Hearings and witnesses.
Section 543.075 - Definitions for ORS 543.075 to 543.092.
Section 543.078 - Annual fee for hydroelectric project.
Section 543.080 - Project specific fees; summary of project specific expenditures.
Section 543.082 - Invoice for fees; overdue fee; interest on delinquent fees.
Section 543.085 - Periodic review of annual fee.
Section 543.088 - Payment of costs or fee for reauthorization or relicensing of project.
Section 543.095 - Challenges to certain statutes related to hydroelectric projects.
Section 543.160 - Hydroelectric facility on North Santiam River prohibited; exception.
Section 543.165 - Hydroelectric facility on part of Deschutes River prohibited.
Section 543.170 - Hydroelectric facility on Isqúulktpe Creek prohibited.
Section 543.210 - Preliminary permits; application; contents; fee.
Section 543.220 - Notice of filing of application; waiting period.
Section 543.225 - Hearing on application; notice; policy.
Section 543.230 - Hearings on application; rules; protest.
Section 543.280 - Fee payments by licensee.
Section 543.300 - Conditions governing license; fees; waiver of conditions.
Section 543.525 - ORS 543.530 to 543.550 not applicable to regulated utilities.
Section 543.610 - Acquisition of project by state or municipality.
Section 543.655 - Definitions for ORS 543.650 to 543.685.
Section 543.665 - Authority to issue revenue bonds to acquire hydroelectric facilities.
Section 543.685 - District board to require weatherization; Weatherization Fund; purpose.