(a) The actual cost of the Hydroelectric Application Review Team’s reauthorization activities for the year in question as established pursuant to ORS 543A.405 and 543A.410; or
(b) 12.5 cents per theoretical horsepower as specified in the water right for each project under consideration for reauthorization. This amount shall be calculated in 1998 dollars.
(2) For any project, the interim period referred to in subsection (1) of this section shall begin on the January 1 immediately following submission to the Water Resources Department of a proposed final order for reauthorization of the project under ORS 543A.115 (2). For any project, the interim period referred to in subsection (1) of this section shall end on December 31 of the year the department issues a final order on reauthorization of the project pursuant to ORS 543A.130.
(3) Notwithstanding ORS 543.090, during each year of the interim period established in subsection (4) of this section, any power claimant or uncertificated claimant seeking to relicense a federally licensed hydroelectric project shall pay the greater of:
(a) The actual cost of the team’s relicensing activities for the year in question as established pursuant to ORS 543.090; or
(b) 12.5 cents per theoretical horsepower as specified in the water right for each project under consideration for relicensing. This amount shall be calculated in 1998 dollars.
(4) For any project, the interim period referred to in subsection (3) of this section shall begin on the January 1 immediately following issuance of an annual license for the project by the Federal Energy Regulatory Commission. For any project, the interim period referred to in subsection (3) of this section shall end on December 31 of the year the Federal Energy Regulatory Commission issues a new license for the project.
(5) The Water Resources Department shall reimburse a participating agency for costs incurred in the agency’s review of a project during the year for which the fees are collected. Such costs shall not include expenses of other state agencies for which a fee is otherwise collected under state law. Any fees collected under subsection (1) or (3) of this section in excess of the team’s actual cost of evaluation of the project for the year shall be distributed according to ORS 536.015.
(6) No fee shall be charged under this section unless the project is a federally licensed project.
(7) No fee shall be charged pursuant to subsection (1) of this section unless the Hydroelectric Application Review Team proposes to reauthorize the water right for the project in the proposed final order submitted to the Water Resources Department under ORS 543A.115 (2).
(8) Water right certificants and licensees with water rights or licenses that expire more than five years after the original federal license for the project expires shall not begin paying fees assessed under this section until after the expiration date of the original state hydroelectric license or water right. [1999 c.873 §9]
Structure 2021 Oregon Revised Statutes
Volume : 15 - Water Resources, Agriculture and Food
Chapter 543 - Hydroelectric Projects
Section 543.010 - Definitions for ORS 543.010 to 543.610.
Section 543.012 - Applicability of chapter to reauthorization of existing hydroelectric project.
Section 543.013 - Applicability of chapter and ORS chapter 543A to ocean renewable energy facility.
Section 543.055 - Hearings and witnesses.
Section 543.075 - Definitions for ORS 543.075 to 543.092.
Section 543.078 - Annual fee for hydroelectric project.
Section 543.080 - Project specific fees; summary of project specific expenditures.
Section 543.082 - Invoice for fees; overdue fee; interest on delinquent fees.
Section 543.085 - Periodic review of annual fee.
Section 543.088 - Payment of costs or fee for reauthorization or relicensing of project.
Section 543.095 - Challenges to certain statutes related to hydroelectric projects.
Section 543.160 - Hydroelectric facility on North Santiam River prohibited; exception.
Section 543.165 - Hydroelectric facility on part of Deschutes River prohibited.
Section 543.170 - Hydroelectric facility on Isqúulktpe Creek prohibited.
Section 543.210 - Preliminary permits; application; contents; fee.
Section 543.220 - Notice of filing of application; waiting period.
Section 543.225 - Hearing on application; notice; policy.
Section 543.230 - Hearings on application; rules; protest.
Section 543.280 - Fee payments by licensee.
Section 543.300 - Conditions governing license; fees; waiver of conditions.
Section 543.525 - ORS 543.530 to 543.550 not applicable to regulated utilities.
Section 543.610 - Acquisition of project by state or municipality.
Section 543.655 - Definitions for ORS 543.650 to 543.685.
Section 543.665 - Authority to issue revenue bonds to acquire hydroelectric facilities.
Section 543.685 - District board to require weatherization; Weatherization Fund; purpose.