This article does not apply to an action:
(1) Against a contractor for which a claimant, as a consumer, is entitled to a specific remedy pursuant to Chapter 46A of this code;
(2) Against a contractor who is not licensed under the provisions of 30-42-1 et seq., of this code;
(3) Demanding damages of $5,000 or less;
(4) Alleging a construction defect that poses an imminent threat of injury to person or property;
(5) Alleging a construction defect that causes property not to be habitable;
(6) Against a contractor who failed to provide the notice required by 21-11A-5 or 21-11A-6 of this code;
(7) Against a contractor if the parties to the contract agreed to submit claims to mediation, arbitration, or another type of alternative dispute resolution; or
(8) Alleging claims for personal injury or death.
Structure West Virginia Code
Article 11A. Notice and Opportunity to Cure Construction Defects
§21-11A-2. Applicability of Article
§21-11A-3. Suit by Contractor; Perfecting Mechanic's Lien
§21-11A-4. Applicability of Definitions; Definitions
§21-11A-5. Contract for Residential Improvements; Notice
§21-11A-6. Contractor Notification Requirements for a New Residential Dwelling Constructed for Sale
§21-11A-7. Prerequisites to Commencing an Action
§21-11A-8. Notice of Claim of Construction Defect
§21-11A-9. Service on Additional Parties
§21-11A-10. Request for Voluntary Disclosure of Additional Information
§21-11A-13. Conduct of Negotiation
§21-11A-14. Settlement Agreement
§21-11A-15. Costs of Negotiation
§21-11A-16. Commencement of Action
§21-11A-17. Additional Construction Defects; Additional Notice of Claim