§ 4007. Disputes; penalties; attorney’s fees
(a) Nothing in this chapter shall prevent an owner, contractor, or subcontractor from withholding payment in whole or in part under a construction contract in an amount equalling the value of any good faith claims against an invoicing contractor or subcontractor, including claims arising from unsatisfactory job progress, defective construction, disputed work, or third-party claims.
(b) If arbitration or litigation is commenced to recover payment due under the terms of this chapter and it is determined that an owner, contractor, or subcontractor has failed to comply with the payment terms of this chapter, the arbitrator or court shall award, in addition to all other damages due and as a penalty, an amount equal to one percent per month of all sums as to which payment has wrongfully been withheld. An amount shall not be deemed to have been wrongfully withheld to the extent it bears a reasonable relation to the value of any claim held in good faith by the owner, contractor, or subcontractor against which an invoicing contractor, or subcontractor is seeking to recover payment.
(c) Notwithstanding any contrary agreement, the substantially prevailing party in any proceeding to recover any payment within the scope of this chapter shall be awarded reasonable attorney’s fees in an amount to be determined by the court or arbitrator, together with expenses. (Added 1991, No. 74, § 1, eff. Jan. 1, 1992.)
Structure Vermont Statutes
Chapter 102 - Construction Contracts
§ 4002. Owner’s payment obligations
§ 4003. Contractor’s and subcontractor’s payment obligations
§ 4004. Errors in documentation
§ 4005a. Fund held in trust; commingling; no effect on title to real property
§ 4006. Prepayment; advance payment
§ 4007. Disputes; penalties; attorney’s fees