Sec. 58.055. RATE ADJUSTMENT BY COMPANY. (a) An electing company may increase a rate for a basic network service during the election period prescribed by Section 58.054 only:
(1) with commission approval that the proposed change is included in Section 58.056, 58.057, or 58.058; and
(2) as provided by Sections 58.056, 58.057, 58.058, and 58.059.
(b) Notwithstanding Subchapter F, Chapter 60, an electing company may, on its own initiative, decrease a rate for a basic network service during the electing period.
(c) The company may decrease the rate for a basic local telecommunications service to an amount above the service's appropriate cost. If the company has been required to perform or has elected to perform a long run incremental cost study, the appropriate cost for the service is the service's long run incremental cost.
Acts 1997, 75th Leg., ch. 166, Sec. 1, eff. Sept. 1, 1997. Amended by Acts 1999, 76th Leg., ch. 1212, Sec. 40, eff. Sept. 1, 1999.
Structure Texas Statutes
Title 2 - Public Utility Regulatory Act
Subtitle C - Telecommunications Utilities
Chapter 58 - Incentive Regulation
Subchapter C. Basic Network Services
Section 58.051. Services Included
Section 58.052. Regulation of Services
Section 58.053. Investment Limitation on Service Standards
Section 58.055. Rate Adjustment by Company
Section 58.056. Rate Adjustment for Changes in Fcc Separations
Section 58.057. Rate Adjustment for Certain Companies
Section 58.058. Rate Group Reclassification
Section 58.059. Commission Rate Adjustment Procedure
Section 58.060. Rate Adjustment After Cap Expiration