Sec. 53.234. TIME FOR NOTICE. The lien claimant must give notice not later than the 15th day of the second month following the month in which the labor was performed or the material furnished.
Acts 1983, 68th Leg., p. 3555, ch. 576, Sec. 1, eff. Jan. 1, 1984. Amended by Acts 1989, 71st Leg., ch. 1138, Sec. 36, eff. Sept. 1, 1989.
Amended by:
Acts 2009, 81st Leg., R.S., Ch. 1304 (H.B. 2515), Sec. 3, eff. September 1, 2009.
Structure Texas Statutes
Title 5 - Exempt Property and Liens
Chapter 53 - Mechanic's, Contractor's, or Materialman's Lien
Subchapter J. Lien on Money Due Public Works Contractor
Section 53.232. To Whom Notice Given; Manner
Section 53.233. Contents of Notice
Section 53.234. Time for Notice
Section 53.235. Official to Retain Funds
Section 53.236. Bond for Release of Lien
Section 53.237. Bond Requirements