Sec. 53.158. PERIOD FOR BRINGING SUIT TO FORECLOSE LIEN. (a) Except as provided by Subsection (a-2), suit must be brought to foreclose the lien not later than the first anniversary of the last day a claimant may file the lien affidavit under Section 53.052.
(a-1) Notwithstanding Section 16.069, Civil Practice and Remedies Code, or any other law, if suit is pursued solely to discharge a lien because limitations have expired on bringing a lien foreclosure suit, the lien claimant's rights to pursue a suit to foreclose a lien are not revived.
(a-2) The limitations period established under Subsection (a) may be extended to not later than the second anniversary of the date the claimant filed the lien affidavit under Section 53.052 if, before the expiration of the limitations period established under Subsection (a), the claimant enters into a written agreement with the then-current record owner of the property to extend the limitations period. The agreement must be recorded with the clerk of the same county where the lien was recorded and is considered to be notice of the extension to any subsequent purchaser.
(b) Repealed by Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 36(9), eff. January 1, 2022.
Added by Acts 1989, 71st Leg., ch. 1138, Sec. 23, eff. Sept. 1, 1989. Amended by Acts 1997, 75th Leg., ch. 526, Sec. 16, eff. Sept. 1, 1997; Acts 1999, 76th Leg., ch. 889, Sec. 4, eff. Sept. 1, 1999.
Amended by:
Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 23, eff. January 1, 2022.
Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 36(9), eff. January 1, 2022.
Structure Texas Statutes
Title 5 - Exempt Property and Liens
Chapter 53 - Mechanic's, Contractor's, or Materialman's Lien
Subchapter G. Release and Foreclosure; Action on Claim
Section 53.151. Enforcement of Remedies Against Money Due Original Contractor or Subcontractor
Section 53.152. Release of Claim or Lien
Section 53.153. Defense of Actions
Section 53.155. Transfer of Property Sold
Section 53.156. Costs and Attorney's Fees
Section 53.157. Discharge of Lien
Section 53.158. Period for Bringing Suit to Foreclose Lien
Section 53.159. Obligation to Furnish Information
Section 53.160. Summary Motion to Remove Invalid or Unenforceable Lien