Sec. 37.156. INTERFERENCE WITH ANOTHER UTILITY. If an electric utility constructing or extending the utility's lines, plant, or system interferes or attempts to interfere with the operation of a line, plant, or system of another utility, the commission by order may:
(1) prohibit the construction or extension; or
(2) prescribe terms for locating the affected lines, plants, or systems.
Acts 1997, 75th Leg., ch. 166, Sec. 1, eff. Sept. 1, 1997.
Structure Texas Statutes
Title 2 - Public Utility Regulatory Act
Subtitle B - Electric Utilities
Chapter 37 - Certificates of Convenience and Necessity
Subchapter D. Regulation of Services, Areas, and Facilities
Section 37.151. Provision of Service
Section 37.152. Grounds for Reduction of Service
Section 37.153. Required Refusal of Service
Section 37.154. Transfer of Certificate
Section 37.155. Application of Contracts