Sec. 37.052. EXCEPTIONS TO CERTIFICATE REQUIREMENT FOR SERVICE EXTENSION. (a) An electric utility is not required to obtain a certificate for an:
(1) extension into territory that is:
(A) contiguous to the territory the electric utility serves;
(B) not receiving similar service from another electric utility; and
(C) not in another electric utility's certificated area;
(2) extension in or to territory the utility serves or is authorized to serve under a certificate; or
(3) operation, extension, or service in progress on September 1, 1975.
(b) An extension allowed under Subsection (a) is limited to a device used:
(1) to interconnect existing facilities; or
(2) solely to transmit electric utility services from an existing facility to a customer of retail electric utility service.
(c) An electric utility is not required to amend the utility's certificate of public convenience and necessity to construct a transmission line that connects the utility's existing transmission facilities to a substation or metering point if:
(1) the transmission line does not exceed:
(A) three miles in length, if the line connects to a load-serving substation or metering point; or
(B) two miles in length, if the line connects to a generation substation or metering point;
(2) each landowner whose property would be directly affected by the transmission line, as provided by commission rules, provides written consent for the transmission line; and
(3) all rights-of-way necessary for construction of the transmission line have been purchased.
Acts 1997, 75th Leg., ch. 166, Sec. 1, eff. Sept. 1, 1997.
Amended by:
Acts 2021, 87th Leg., R.S., Ch. 876 (S.B. 1281), Sec. 1, eff. September 1, 2021.
Structure Texas Statutes
Title 2 - Public Utility Regulatory Act
Subtitle B - Electric Utilities
Chapter 37 - Certificates of Convenience and Necessity
Subchapter B. Certificate of Convenience and Necessity
Section 37.051. Certificate Required
Section 37.052. Exceptions to Certificate Requirement for Service Extension
Section 37.0521. Exception for Retail Sales by Certain Qualifying Cogenerators
Section 37.053. Application for Certificate
Section 37.054. Notice and Hearing on Application
Section 37.0541. Consolidation of Certain Proceedings
Section 37.055. Request for Preliminary Order
Section 37.056. Grant or Denial of Certificate
Section 37.057. Deadline for Application for New Transmission Facility