Sec. 36.205. PURCHASED POWER COST RECOVERY. (a) This section applies only to an increase or decrease in the cost of purchased electricity that has been:
(1) accepted by a federal regulatory authority; or
(2) approved after a hearing by the commission.
(b) The commission may use any appropriate method to provide for the adjustment of the cost of purchased electricity on terms determined by the commission.
(c) Purchased electricity costs may be recovered:
(1) concurrently with the effective date of the changed costs to the purchasing electric utility; or
(2) as soon after the effective date as reasonably practical.
(d) The commission may provide a mechanism to allow an electric utility that has a noncontiguous geographical service area and that purchases power for resale for that noncontiguous service area from electric utilities that are not members of the Electric Reliability Council of Texas to recover purchased power costs for the area in a manner that reflects the purchased power cost for that specific geographical noncontiguous area. The commission may not require an electric cooperative corporation to use the mechanism provided under this section unless the electric cooperative corporation requests its use.
Acts 1997, 75th Leg., ch. 166, Sec. 1, eff. Sept. 1, 1997.
Structure Texas Statutes
Title 2 - Public Utility Regulatory Act
Subtitle B - Electric Utilities
Subchapter E. Cost Recovery and Rate Adjustment
Section 36.201. Automatic Adjustment for Changes in Costs
Section 36.202. Adjustment for Change in Tax Liability
Section 36.203. Fuel Cost Recovery; Adjustment of Fuel Factor
Section 36.204. Cost Recovery and Incentives
Section 36.205. Purchased Power Cost Recovery
Section 36.207. Use of Mark-Ups
Section 36.208. Payment to Qualifying Facility
Section 36.209. Recovery by Certain Non-Ercot Utilities of Certain Transmission Costs
Section 36.210. Periodic Rate Adjustments
Section 36.211. Relation Back of Rates for Certain Non-Ercot Utilities
Section 36.212. Rate Case Requirement for Certain Non-Ercot Utilities
Section 36.213. Adjustment for Cybersecurity Monitor Costs for Certain Utilities
Section 36.214. Recovery of Generation Investment by Non-Ercot Utilities