Sec. 271.060.  CHANGE ORDERS.  (a)  After performance of a construction contract begins, a governing body may approve change orders if necessary to:
(1)  make changes in plans or specifications;  or
(2)  decrease or increase the quantity of work to be performed or materials, equipment, or supplies to be furnished.
(b)  The total price of a contract may not be increased by a change order unless provision has been made for the payment of the added cost by the appropriation of current funds or bond funds for that purpose, by the authorization of the issuance of certificates, or by a combination of those procedures.
(c)  A contract with an original contract price of $1 million or more may not be increased by more than 25 percent.  If a change order for a contract with an original contract price of less than $1 million increases the contract amount to $1 million or more, subsequent change orders may not increase the revised contract amount by more than 25 percent.
(d)  A governing body may grant authority to an official or employee responsible for purchasing or for administering a contract to approve a change order that involves an increase or decrease of $50,000 or less.
Acts 1987, 70th Leg., ch. 149, Sec. 1, eff. Sept. 1, 1987.
Amended by: 
Acts 2011, 82nd Leg., R.S., Ch. 479 (H.B. 679), Sec. 2, eff. June 17, 2011.
Acts 2011, 82nd Leg., R.S., Ch. 1129 (H.B. 628), Sec. 2.11, eff. September 1, 2011.
Acts 2013, 83rd Leg., R.S., Ch. 161 (S.B. 1093), Sec. 22.001(34), eff. September 1, 2013.
Structure Texas Statutes
Title 8 - Acquisition, Sale, or Lease of Property
Subchapter C. Certificate of Obligation Act
Section 271.042. Purpose; Conflict
Section 271.044. Subchapter Available to Certain Municipalities
Section 271.045. Purposes for Which Certificates May Be Authorized
Section 271.046. Additional Purposes for Certificates
Section 271.048. Claims and Accounts; Funding and Exchange
Section 271.049. Notice of Intention to Issue Certificates; Petition and Election
Section 271.050. Sale of Certificates
Section 271.051. Certificates as Investments or as Security for Deposits
Section 271.052. Certificates Payable From and Secured by Other Revenues
Section 271.0525. Refinancing Certificates Issued by County
Section 271.053. Certificates as Debt and Security
Section 271.054. Competitive Procurement Requirement
Section 271.055. Notice to Bidders
Section 271.056. Exemptions From Advertisement Requirement
Section 271.0565. Pre-Bid Conference
Section 271.057. Award of Contract
Section 271.058. Authority to Reject Bids
Section 271.059. Contractor's Bonds
Section 271.060. Change Orders
Section 271.061. Compensation on Unit Price Contracts
Section 271.062. Certain Contracts Not Required to Be in Writing
Section 271.063. Unconstitutional Procedure Corrected by Resolution of Issuer