Sec. 232.003. SUBDIVISION REQUIREMENTS. By an order adopted and entered in the minutes of the commissioners court, and after a notice is published in a newspaper of general circulation in the county, the commissioners court may:
(1) require a right-of-way on a street or road that functions as a main artery in a subdivision, of a width of not less than 50 feet or more than 100 feet;
(2) require a right-of-way on any other street or road in a subdivision of not less than 40 feet or more than 70 feet;
(3) require that the shoulder-to-shoulder width on collectors or main arteries within the right-of-way be not less than 32 feet or more than 56 feet, and that the shoulder-to-shoulder width on any other street or road be not less than 25 feet or more than 35 feet;
(4) adopt, based on the amount and kind of travel over each street or road in a subdivision, reasonable specifications relating to the construction of each street or road;
(5) adopt reasonable specifications to provide adequate drainage for each street or road in a subdivision in accordance with standard engineering practices;
(6) require that each purchase contract made between a subdivider and a purchaser of land in the subdivision contain a statement describing the extent to which water will be made available to the subdivision and, if it will be made available, how and when;
(7) require that the owner of the tract to be subdivided execute a good and sufficient bond in the manner provided by Section 232.004;
(8) adopt reasonable specifications that provide for drainage in the subdivision to:
(A) efficiently manage the flow of stormwater runoff in the subdivision; and
(B) coordinate subdivision drainage with the general storm drainage pattern for the area; and
(9) require lot and block monumentation to be set by a registered professional surveyor before recordation of the plat.
Acts 1987, 70th Leg., ch. 149, Sec. 1, eff. Sept. 1, 1987. Amended by Acts 1989, 71st Leg., ch. 1, Sec. 54(b), eff. Aug. 28, 1989; Acts 1989, 71st Leg., ch. 624, Sec. 3.04, eff. Sept. 1, 1989; Acts 1999, 76th Leg., ch. 129, Sec. 4, eff. Sept. 1, 1999.
Structure Texas Statutes
Title 7 - Regulation of Land Use, Structures, Businesses, and Related Activities
Subtitle B - County Regulatory Authority
Chapter 232 - County Regulation of Subdivisions
Subchapter A. Subdivision Platting Requirements in General
Section 232.001. Plat Required
Section 232.0015. Exceptions to Plat Requirement
Section 232.002. Approval by County Required
Section 232.0021. Plat Application Fee
Section 232.0023. Approval Procedure: Applicability
Section 232.0025. Approval Procedure: Timely Approval of Plats and Plans
Section 232.0026. Approval Procedure: Conditional Approval or Disapproval Requirements
Section 232.0027. Approval Procedure: Applicant Response to Conditional Approval or Disapproval
Section 232.0028. Approval Procedure: Approval or Disapproval of Response
Section 232.00285. Development Plan Review
Section 232.0029. Judicial Review of Disapproval
Section 232.003. Subdivision Requirements
Section 232.0031. Standard for Roads in Subdivision
Section 232.0032. Additional Requirements: Use of Groundwater
Section 232.0033. Additional Requirements: Future Transportation Corridors
Section 232.0034. Additional Requirements: Access by Emergency Vehicles
Section 232.004. Bond Requirements
Section 232.0045. Financial Guarantee in Lieu of Bond
Section 232.0048. Conflict of Interest; Penalty
Section 232.005. Enforcement in General; Penalty
Section 232.006. Exceptions for Populous Counties or Contiguous Counties
Section 232.007. Manufactured Home Rental Communities
Section 232.008. Cancellation of Subdivision
Section 232.0083. Cancellation of Certain Subdivision Plats if Existing Plat Obsolete
Section 232.0085. Cancellation of Certain Subdivisions if Land Remains Undeveloped
Section 232.009. Revision of Plat
Section 232.0095. Alternative Procedures for Plat Revision
Section 232.010. Exception to Plat Requirement: County Determination