Sec. 2253.071. TERMINATION OR ABANDONMENT OF CONTRACT; PROCEEDS OF CONTRACT. (a) The proceeds of a public work contract are not payable, until all costs of completion of the contract work are paid by the contractor or the contractor's surety, to a contractor who furnishes a bond required by this chapter if:
(1) the contractor abandons performance of the contract; or
(2) the contractor's right to proceed with performance of the contract is lawfully terminated by the awarding governmental entity because of the contractor's default.
(b) The balance of the public work contract proceeds remaining after the costs of completion are paid shall be paid according to the contractor's and the surety's interests as may be established by agreement or by judgment of a court.
(c) A surety that completes a public work contract or incurs a loss under a performance bond required under this chapter has a claim to the proceeds of the contract prior to all other creditors of the prime contractor to the full extent of the surety's loss. That priority does not excuse the surety from paying an obligation under a payment bond.
Added by Acts 1993, 73rd Leg., ch. 268, Sec. 1, eff. Sept. 1, 1993.
Structure Texas Statutes
Subtitle F - State and Local Contracts and Fund Management
Chapter 2253 - Public Work Performance and Payment Bonds
Subchapter D. Claims on Bonds; Enforcement
Section 2253.071. Termination or Abandonment of Contract; Proceeds of Contract
Section 2253.072. State Not Liable for Costs
Section 2253.073. Suit on Payment Bond
Section 2253.074. Costs and Attorney Fees
Section 2253.075. Assignment of Claim
Section 2253.076. Limitations on Certain Claims; Maximum Retainage
Section 2253.078. Statute of Limitations
Section 2253.079. Criminal Offense for False and Fraudulent Claim