5-22-8. Discharge of lien.
Any such lien may be discharged:
(1)By filing with the officer with whom the liens shall be filed a certificate of satisfaction of the claimant or his successor in interest duly acknowledged;
(2)By lapse of the time within which an action to enforce the same may be commenced without such action having been commenced;
(3)By satisfaction of any judgment that may be rendered in any action to foreclose such lien.
Source: SL 1895, ch 133, §6; RCCivP 1903, §718; RC 1919, §1665; SDC 1939, §39.0908.