South Dakota Codified Laws
Chapter 47 - Stray Electrical Current And Voltage Remediation
Section 49-47-4 - Complaint of failure to comply with chapter--Decision by commission.

49-47-4. Complaint of failure to comply with chapter--Decision by commission.
A dairy producer or utility may file a complaint with the commission claiming that there has been a failure to comply with this chapter. The commission has exclusive, initial jurisdiction to determine:
(1)Whether the dairy producer has provided the requisite notice to the electric utility;
(2)Whether the dairy producer has cooperated with the electric utility to allow the utility to complete measuring and testing;
(3)Whether a utility has complied with the commission rules regarding measurement of stray current or voltage;
(4)Whether the utility's measurements demonstrated stray current or voltage at or above the preventive action level;
(5)Whether the utility has properly identified that portion of the stray current or voltage at cow contact points attributable to the utility's distribution system; and
(6)Whether the utility has complied with its remediation obligation under this chapter.
After opportunity for hearing, the commission shall issue a decision finding whether this chapter has been complied with or not. If one or more provisions of this chapter have not been complied with, the commission shall order compliance within a period of time prescribed by the commission. The commission shall assess its costs associated with the complaint equally between the dairy producer and the utility.

Source: SL 2015, ch 237, ยง4.