49-34A-17. Implementation of proposed practice, proposed rate, or lower rate--Rate design--Accounts of customer payments--Refund of excess--Time limit.
The public utility may implement the proposed practice, the proposed rate, or a rate lower than the proposed rate if:
(1)The proposed rate or practice has not been suspended or is no longer subject to suspension;
(2)The commission has not issued a final decision; and
(3)Thirty days has passed from the date of filing.
If the public utility implements the proposed rate or a rate lower than the proposed rate, the public utility shall use the same rate design that is currently in effect or the rate design that the public utility proposed when the public utility filed for the increased rate. If the public utility uses a rate design different than the rate design currently in effect or the rate design the public utility proposed when the public utility filed for the increased rate, commission approval is needed prior to implementation.
In the case of a proposed increased rate, the commission may, by order, require the public utility to keep an accurate account in detail of all amounts received by reason of the increase, specifying by whom and in whose behalf the amounts are paid. Upon completion of the hearings and decision, the commission may by further order require the public utility to refund, with interest, to customers, the portion of the increased rates found to be unjust, unreasonable, or discriminatory. The refund shall be carried out as provided in §§49-34A-22 and 49-34A-23. If the commission does not issue a final decision within twelve months from the date the proposed rate or practice was filed, the commission may not require a refund of increased rates charged after the twelve months.
Source: SL 1975, ch 283, §8; SL 1976, ch 296, §17; SL 1977, ch 392, §1; SL 2008, ch 242, §2; SL 2011, ch 209, §1.
Structure South Dakota Codified Laws
Title 49 - Public Utilities and Carriers
Chapter 34A - Gas And Electric Utilities Regulation
Section 49-34A-1 - Definition of terms.
Section 49-34A-2 - Service required of utilities.
Section 49-34A-4 - Regulatory powers of commission--Rules.
Section 49-34A-5 - Municipal authority terminated.
Section 49-34A-6 - Rates to be reasonable and just--Regulation by commission.
Section 49-34A-7 - System of accounts.
Section 49-34A-8 - Criteria for determination of rates by commission.
Section 49-34A-8.1 - Policy to alleviate financial burden of pricing structure.
Section 49-34A-8.2 - Incentive rates for improved performance and efficiency.
Section 49-34A-8.3 - Business development rates--Public interest exception.
Section 49-34A-8.4 - Burden on public utility to establish criteria for determination of rates.
Section 49-34A-10 - Tariffs and schedules filed by utilities--Public inspection.
Section 49-34A-11 - Burden of proving reasonableness of rates.
Section 49-34A-12 - Change in rates--Notice to commission and affected customers.
Section 49-34A-13 - Hearing on rate changes.
Section 49-34A-14 - Suspension of proposed rate or practice pending hearing--Time.
Section 49-34A-20 - Rate increases not required to prevent competition.
Section 49-34A-21 - Determination of rates--Order--Maximum rate--Classification adjustment.
Section 49-34A-24 - Municipal taxes on utilities passed on to customers.
Section 49-34A-25.2 - Approval, rejection, or modification of certain tariffs--Notice and hearing.
Section 49-34A-25.3 - Filing for annual rate adjustments--Contents.
Section 49-34A-25.4 - Standards for approval of annual rate adjustments.
Section 49-34A-26 - Investigation of rates or services by commission--Notice--Action.
Section 49-34A-31 - Prompt disposition of applications on securities and obligations--Continuance.
Section 49-34A-32 - Findings required to permit issue of securities or assumption of obligation.
Section 49-34A-36 - Investigation of proposed disposition of property--Time for decision.
Section 49-34A-39 - Investigation of condition of public utilities--Hearings.
Section 49-34A-41 - Order for production of utility books and records--Out-of-state records.
Section 49-34A-47 - Time of payments to municipality.
Section 49-34A-48 - Electric utility's right to continue service in area annexed to municipality.
Section 49-34A-49 - Municipal offer to purchase electric facilities in annexed area.
Section 49-34A-50 - Purchase price for electric facilities in area annexed by municipality.
Section 49-34A-54 - Purchase by utility of areas disannexed by municipality.
Section 49-34A-57 - Extension of lines to serve utility's or municipality's own property.
Section 49-34A-59 - Notice and hearing on violation of service area provisions--Time for decision.
Section 49-34A-61 - Burden of proof on party seeking to modify or vacate commission order.
Section 49-34A-62 - Parties entitled to rehearings and appeals--Procedure.
Section 49-34A-66 - Violation of law or commission order--Civil penalty.
Section 49-34A-67 - Each violation or day's continuation as separate offense.
Section 49-34A-68 - Penalties cumulative--Single action does not bar other remedies.
Section 49-34A-69 - Commission to refer violations to attorney general.
Section 49-34A-70 - Preference on calendar for proceedings under chapter.
Section 49-34A-72 - Commission participation in federal proceedings--Recovery of expenses.
Section 49-34A-73 - Phase in rate plan for rate increases due to plant additions.
Section 49-34A-73.1 - Plant additions defined.
Section 49-34A-74 - Approval of phase in rate plan--Conditions.
Section 49-34A-75 - Review of reasonableness of rates under phase in rate plan--Adjustment.
Section 49-34A-76 - Filing of general rate case after end of phase in rate plan--Exception.
Section 49-34A-77 - Filing fee for phase in rate plan.
Section 49-34A-78 - Nonapproval of application for phase in rate plan.
Section 49-34A-79 - Public or electric utilities authorized to remove certain obstructions.
Section 49-34A-82 - Definitions.
Section 49-34A-84 - Requirements for refund.
Section 49-34A-85 - Amount of refund.
Section 49-34A-86 - Application for refund--Refund claim not assignable--Exception.
Section 49-34A-87 - Secretary to prescribe form and documentation requirements.
Section 49-34A-89 - Withheld amounts paid at completion of project.
Section 49-34A-90 - Fraudulent claim--Refunded sums constitute lien in favor of state.
Section 49-34A-91 - Right to hearing on denial of refund claim.
Section 49-34A-92 - Promulgation of rules.
Section 49-34A-93 - Implementation of and compliance with certain federal energy acts.
Section 49-34A-94 - Renewable electricity and recycled energy defined.
Section 49-34A-95 - Renewable energy credits for electricity authorized.
Section 49-34A-96 - Promulgation of rules regarding renewable energy credit system.
Section 49-34A-98 - Approval, rejection, or modification of certain electric service tariffs.
Section 49-34A-99 - Annual rate adjustment filings for certain electric service tariffs.
Section 49-34A-100 - Approval, rejection, or modification of annual rate adjustment.
Section 49-34A-101 - State renewable, recycled, and conserved energy objective established.
Section 49-34A-102 - Qualifications for meeting renewable, recycled, and conserved energy objective.
Section 49-34A-104 - Evaluation of use as reasonable and cost effective.
Section 49-34A-105 - Annual reports concerning renewable, recycled, and conserved energy objective.
Section 49-34A-106 - Purchase and retirement of renewable energy and recycled energy credits.
Section 49-34A-107 - Separation and protection of assets of gas and electric utilities.
Section 49-34A-109 - Definitions.
Section 49-34A-110 - Responsibility for safety and reliability of farm tap distribution system.
Section 49-34A-111 - Liability of farm tap service provider.
Section 49-34A-116 - Electric vehicle charging station--Electric utility--Exception.