10-35-1.3. Definitions.
Terms as used in §§10-35-1.3 to 10-35-1.6, inclusive, mean:
(1)"Commercial operation date," the first date that a power generation facility is producing electricity on a continuous basis and is delivering electricity to customers;
(2)"Construction date," is the first date earth is excavated for the purpose of constructing the power generation facility;
(3)"Construction period," the time period between the construction date and the commercial operation date;
(4)"Nameplate capacity," the number of kilowatts a power generation facility can produce, as assigned to the power unit by the manufacturer and determined by the secretary;
(5)"Power generation facility," a facility with one power unit that generates electricity, with a nameplate capacity of no less than five hundred megawatts or a facility that generates at least five hundred megawatts of electricity by converting coal to synthesis gas which is used to fuel a combined-cycle power unit that generates electricity from one or more combustion turbines and one or more steam turbines;
(6)"Secretary," the secretary of the Department of Revenue.
Source: SL 2005, ch 66, §1; SL 2007, ch 53, §1; SL 2011, ch 1 (Ex. Ord. 11-1), §161, eff. Apr. 12, 2011.
Structure South Dakota Codified Laws
Chapter 35 - Taxation Of Electric, Heating, Water And Gas Companies
Section 10-35-1 - Companies subject to tax.
Section 10-35-1.2 - Generating property of rural electric companies subject to tax.
Section 10-35-1.3 - Definitions.
Section 10-35-1.5 - Partial exemption for power generation facility--Allocation of exemption.
Section 10-35-1.7 - Definitions.
Section 10-35-1.10 - Promulgation of rules on environmental upgrade exemption.
Section 10-35-2 - Operating property assessed by department.
Section 10-35-3 - Annual report required of companies--Date of filing.
Section 10-35-4 - Information given in annual report on property within municipalities.
Section 10-35-5 - Information given in annual report on property outside municipalities.
Section 10-35-6 - Capitalization and financial data given in annual report.
Section 10-35-7 - Additional information given in annual report.
Section 10-35-8 - Addition to assessable value for failure to file annual report.
Section 10-35-10 - Valuation of power and pipelines--Application of property tax levies.
Section 10-35-10.1 - Determining fair market value of public utility property.
Section 10-35-11 - Notice of assessment to company--Hearing.
Section 10-35-15 - Collection of delinquent taxes.
Section 10-35-16 - Definition of terms.
Section 10-35-17 - Alternative annual tax on wind farm property and solar facilities.
Section 10-35-18 - Annual tax based on nameplate capacity of wind farm or solar facility.
Section 10-35-20 - Renewable facility tax fund.
Section 10-35-21 - Distributions from renewable facility tax fund.