RCW 60.04.230
Construction projects—Notice to be posted by prime contractor—Penalty.
(1) For any construction project costing more than five thousand dollars the prime contractor shall post in plain view for the duration of the construction project a legible notice at the construction jobsite containing the following:
(a) The legal description, or the tax parcel number assigned pursuant to RCW 84.40.160, and the street address if available, and may include any other identification of the construction site by the prime contractor;
(b) The property owner's name, address, and phone number;
(c) The prime contractor's business name, address, phone number, current state contractor registration number and identification; and
(d) Either:
(i) The name, address, and phone number of the office of the lender administering the interim construction financing, if any; or
(ii) The name and address of the firm that has issued a payment bond, if any, on behalf of the prime contractor for the protection of the owner if the bond is for an amount not less than fifty percent of the total amount of the construction project.
(2) For any construction project which requires a building permit under local ordinance, compliance with the posting requirements of RCW 19.27.095 shall constitute compliance with this section. Otherwise, the information shall be posted as set forth in this section.
(3) Failure to comply with this section shall subject the prime contractor to a civil penalty of not more than five thousand dollars, payable to the county where the project is located.
[ 1991 c 281 § 28; 1984 c 202 § 3.]
Structure Revised Code of Washington
Chapter 60.04 - Mechanics' and Materialmen's Liens.
60.04.031 - Notices—Exceptions.
60.04.035 - Acts of coercion—Application of chapter 19.86 RCW.
60.04.041 - Contractor registration.
60.04.051 - Property subject to lien.
60.04.071 - Release of lien rights.
60.04.081 - Frivolous claim—Procedure.
60.04.091 - Recording—Time—Contents of lien.
60.04.101 - Separate residential units—Time for filing.
60.04.131 - Claims—Designation of amount due.
60.04.141 - Lien—Duration—Procedural limitations.
60.04.151 - Rights of owner—Recovery options.
60.04.161 - Bond in lieu of claim.
60.04.171 - Foreclosure—Parties.
60.04.181 - Rank of lien—Application of proceeds—Attorneys' fees.
60.04.190 - Destruction or concealment of property—Removal from premises—Penalty.
60.04.191 - Effect of note—Personal action preserved.
60.04.201 - Material exempt from process—Exception.
60.04.211 - Lien—Effect on community interest.
60.04.221 - Notice to lender—Withholding of funds.
60.04.226 - Financial encumbrances—Priorities.
60.04.230 - Construction projects—Notice to be posted by prime contractor—Penalty.
60.04.250 - Informational materials on construction lien laws—Master documents.
60.04.255 - Informational materials on construction lien laws—Copies—Liability.
60.04.261 - Availability of information.
60.04.900 - Liberal construction—1991 c 281.
60.04.902 - Effective date, application—1991 c 281.