RCW 43.42.080
Participating permit agencies—Timelines.
With the agreement of all participating permitting agencies and the permit applicant or project proponent, state permitting agencies may establish timelines to make permit decisions, including the time periods required to determine that the permit applications are complete, to review the applications, and to process the permits. Established timelines shall not be shorter than those otherwise required for each permit under other applicable provisions of law, but may extend and coordinate such timelines. The goal of the established timelines is to achieve the maximum efficiencies possible through concurrent studies and consolidation of applications, permit review, hearings, and comment periods. A timeline established under this subsection with the agreement of each permitting agency shall commit each permitting agency to act within the established timeline.
[ 2007 c 94 § 9; 2004 c 32 § 1.]
Structure Revised Code of Washington
Title 43 - State Government—Executive
Chapter 43.42 - Office of Regulatory Assistance.
43.42.010 - Office created—Appointment of director—Duties.
43.42.020 - Operating principle—Providing information regarding permits.
43.42.040 - Maintaining and furnishing information—Contact point—Service center—Website.
43.42.050 - Project scoping—Factors.
43.42.060 - Fully coordinated permit process—Requirements—Procedure.
43.42.070 - Cost-reimbursement agreements.
43.42.080 - Participating permit agencies—Timelines.
43.42.090 - Multiagency permitting teams—Findings—Intent—Purpose.
43.42.092 - Multiagency permitting teams.
43.42.095 - Multiagency permitting team account.
43.42.100 - Streamlined process certification.
43.42.900 - Jurisdiction of energy facility site evaluation council not affected.
43.42.901 - Authority of permit agencies not affected.
43.42.902 - Authority of participating permit agency retained.