(a) Phase I compliance.--On or before February 1, 1993, each public utility shall submit to the commission and may request commission approval of a plan to bring its generating units which use coal to generate electricity into compliance with the Phase I requirements of Title IV of the Clean Air Act (Public Law 95-95, 42 U.S.C. § 7651 et seq.).
(b) Phase II compliance.--On or before January 1, 1996, each public utility shall submit to the commission and may request commission approval of a plan to bring its generating units which use coal to generate electricity into compliance with the Phase II requirements of Title IV of the Clean Air Act.
(c) Notice of plan.--At the same time it submits its plan to the commission, the public utility shall provide a copy of the plan to the Department of Environmental Resources, the Consumer Advocate and the Small Business Advocate. For plans submitted after the effective date of this section, the commission shall cause notice of the utility's filing to be published in the Pennsylvania Bulletin. The public utility shall make available, upon request, a copy of the proposed plan to any coal supplier with which it has a supply contract for more than one year and to any collective bargaining representative for the coal supplier.
(d) Review by commission.--
(1) If the utility has requested commission approval of its plan, the commission shall review the proposed plan on an expedited basis to determine if the utility's proposed compliance plan submitted under this section is in the public interest.
(2) After notice and opportunity for a hearing, the commission shall approve or disapprove the compliance plan within nine months after the plan is filed, provided that approval may be in whole or in part and may be subject to such limitations and qualifications as may be deemed necessary and in the public interest. The commission's decision shall establish that the utility's costs of compliance are recoverable costs of service, provided the costs:
(i) are reasonable in amount and prudently incurred as determined in an appropriate rate or other proceeding; and
(ii) represent investment in flue gas desulfurization devices, clean coal technologies or similar facilities designed to maintain or promote the use of coal, including facilities which intermittently or simultaneously burn natural gas with coal.
(3) Costs established as recoverable under paragraph (2) shall qualify as nonrevenue-producing investment to improve environmental conditions under section 1315 (relating to limitation on consideration of certain costs for electric utilities), provided that any benefits to the utility generated by the sale of allowances under the Clean Air Act shall be flowed through to the utility's ratepayers.
(4) The utility shall not be required to refile its plan or to seek additional commission approvals concerning its plan unless the utility's plan is significantly amended or revised.
(e) Definition.--As used in this section, the term "Clean Air Act" means Public Law 95-95, 42 U.S.C. § 7401 et seq. and includes the Clean Air Act Amendments (Public Law 101-549, 104 Stat. 2399) approved November 15, 1990.
(Apr. 16, 1992, P.L.149, No.27, eff. 60 days)
1992 Amendment. Act 27 added section 530.
References in Text. The Department of Environmental Resources, referred to in subsec. (c), was abolished by Act 18 of 1995. Its functions were transferred to the Department of Conservation and Natural Resources and the Department of Environmental Protection.
Structure Pennsylvania Consolidated & Unconsolidated Statutes
Pennsylvania Consolidated & Unconsolidated Statutes
Section 502 - Enforcement proceedings by commission
Section 503 - Enforcement proceedings by Chief Counsel
Section 504 - Reports by public utilities
Section 505 - Duty to furnish information to commission; cooperation in valuing property
Section 506 - Inspection of facilities and records
Section 507 - Contracts between public utilities and municipalities
Section 508 - Power of the commission to vary, reform and revise contracts
Section 509 - Regulation of manufacture, sale or lease of appliances
Section 510 - Assessment for regulatory expenses upon public utilities
Section 511 - Disposition, appropriation and disbursement of assessments and fees
Section 511.1 - Use of Federal funds under energy program
Section 512 - Power of commission to require insurance
Section 512.1 - Power of commission to confiscate, impound and sell vehicles
Section 513 - Public letting of contracts
Section 515 - Construction cost of electric generating units
Section 516 - Audits of certain utilities
Section 517 - Conversion of electric generating units fueled by oil or natural gas
Section 518 - Construction of electric generating units fueled by nuclear energy
Section 519 - Construction of electric generating units fueled by oil or natural gas
Section 521 - Retirement of electric generating units
Section 522 - Expense reduction program
Section 523 - Performance factor consideration
Section 524 - Data to be supplied by electric utilities
Section 525 - Sale of generating units and power
Section 526 - Rejection of rate increase requests due to inadequate quality or quantity of service
Section 527 - Cogeneration rules and regulations
Section 528 - Use of foreign coal by qualifying facilities
Section 529 - Power of commission to order acquisition of small water and sewer utilities