Nevada Revised Statutes
Chapter 701A - Energy-Related Tax Incentives
NRS 701A.365 - Requirements for approval of application; exceptions; submission of annual report to Office of Economic Development. [Effective through June 30, 2032.] Requirements for approval of application; exceptions; submission of annual report t...


1. The Director, in consultation with the Office of Economic Development, shall approve an application for a partial abatement pursuant to NRS 701A.300 to 701A.390, inclusive, if the Director, in consultation with the Office of Economic Development, makes the following determinations:
(a) The applicant has executed an agreement with the Director which must:
(1) State that the facility will, after the date on which the abatement becomes effective, continue in operation in this State for a period specified by the Director, which must be at least 10 years, and will continue to meet the eligibility requirements for the abatement; and
(2) Bind the successors in interest in the facility for the specified period.
(b) The facility is registered pursuant to the laws of this State or the applicant commits to obtain a valid business license and all other permits required by the county, city or town in which the facility operates.
(c) No funding is or will be provided by any governmental entity in this State for the acquisition, design or construction of the facility or for the acquisition of any land therefor, except any private activity bonds as defined in 26 U.S.C. § 141.
(d) Except as otherwise provided in paragraph (e), if the facility will be located in a county whose population is 100,000 or more or a city whose population is 60,000 or more, the facility meets the following requirements:
(1) There will be 75 or more full-time employees working on the construction of the facility during the second quarter of construction, including, unless waived by the Director for good cause, at least 50 percent who are residents of Nevada;
(2) Establishing the facility will require the facility to make a capital investment of at least $10,000,000 in this State in capital assets that will be retained at the location of the facility until at least the date which is 5 years after the date on which the abatement becomes effective;
(3) The average hourly wage that will be paid by the facility to its employees in this State is at least 110 percent of the average statewide hourly wage, excluding management and administrative employees, as established by the Employment Security Division of the Department of Employment, Training and Rehabilitation on July 1 of each fiscal year; and
(4) Except as otherwise provided in subsection 6, the average hourly wage of the employees working on the construction of the facility will be at least 175 percent of the average statewide hourly wage, excluding management and administrative employees, as established by the Employment Security Division of the Department of Employment, Training and Rehabilitation on July 1 of each fiscal year and:
(I) The employees working on the construction of the facility must be provided a health insurance plan that is provided by a third-party administrator and includes health insurance coverage for dependents of the employees; and
(II) The cost of the benefits provided to the employees working on the construction of the facility will meet the minimum requirements for benefits established by the Director by regulation pursuant to NRS 701A.390.
(e) If the facility will be located in a county whose population is less than 100,000, in an area of a county whose population is 100,000 or more that is located within the geographic boundaries of an area that is designated as rural by the United States Department of Agriculture and at least 20 miles outside of the geographic boundaries of an area designated as urban by the United States Department of Agriculture, or in a city whose population is less than 60,000, the facility meets the following requirements:
(1) There will be 50 or more full-time employees working on the construction of the facility during the second quarter of construction, including, unless waived by the Director for good cause, at least 50 percent who are residents of Nevada;
(2) Establishing the facility will require the facility to make a capital investment of at least $3,000,000 in this State in capital assets that will be retained at the location of the facility until at least the date which is 5 years after the date on which the abatement becomes effective;
(3) The average hourly wage that will be paid by the facility to its employees in this State is at least 110 percent of the average statewide hourly wage, excluding management and administrative employees, as established by the Employment Security Division of the Department of Employment, Training and Rehabilitation on July 1 of each fiscal year; and
(4) Except as otherwise provided in subsection 6, the average hourly wage of the employees working on the construction of the facility will be at least 175 percent of the average statewide hourly wage, excluding management and administrative employees, as established by the Employment Security Division of the Department of Employment, Training and Rehabilitation on July 1 of each fiscal year and:
(I) The employees working on the construction of the facility must be provided a health insurance plan that is provided by a third-party administrator and includes health insurance coverage for dependents of the employees; and
(II) The cost of the benefits provided to the employees working on the construction of the facility will meet the minimum requirements for benefits established by the Director by regulation pursuant to NRS 701A.390.
(f) The financial benefits that will result to this State from the employment by the facility of the residents of this State and from capital investments by the facility in this State will exceed the loss of tax revenue that will result from the abatement.
(g) The facility is consistent with the State Plan for Economic Development developed by the Executive Director of the Office of Economic Development pursuant to subsection 2 of NRS 231.053.
2. The Director shall not approve an application for a partial abatement of the taxes imposed pursuant to chapter 361 of NRS submitted pursuant to NRS 701A.360 by a facility for the generation of process heat from solar renewable energy, a wholesale facility for the generation of electricity from renewable energy, a facility for the storage of energy from renewable generation or a hybrid renewable generation and energy storage facility unless the application is approved or deemed approved pursuant to this subsection. The board of county commissioners of a county must provide notice to the Director that the board intends to consider an application and, if such notice is given, must approve or deny the application not later than 30 days after the board receives a copy of the application. The board of county commissioners:
(a) Shall, in considering an application pursuant to this subsection, make a recommendation to the Director regarding the application;
(b) May, in considering an application pursuant to this subsection, deny an application only if the board of county commissioners determines, based on relevant information, that:
(1) The projected cost of the services that the local government is required to provide to the facility will exceed the amount of tax revenue that the local government is projected to receive as a result of the abatement; or
(2) The projected financial benefits that will result to the county from the employment by the facility of the residents of this State and from capital investments by the facility in the county will not exceed the projected loss of tax revenue that will result from the abatement;
(c) Must not condition the approval of the application on a requirement that the facility agree to purchase, lease or otherwise acquire in its own name or on behalf of the county any infrastructure, equipment, facilities or other property in the county that is not directly related to or otherwise necessary for the construction and operation of the facility; and
(d) May, without regard to whether the board has provided notice to the Director of its intent to consider the application, make a recommendation to the Director regarding the application.
If the board of county commissioners does not approve or deny the application within 30 days after the board receives from the Director a copy of the application, the application shall be deemed approved.
3. Notwithstanding the provisions of subsection 1, the Director, in consultation with the Office of Economic Development, may, if the Director, in consultation with the Office, determines that such action is necessary:
(a) Approve an application for a partial abatement for a facility that does not meet any requirement set forth in subparagraph (1) or (2) of paragraph (d) of subsection 1 or subparagraph (1) or (2) of paragraph (e) of subsection 1; or
(b) Add additional requirements that a facility must meet to qualify for a partial abatement.
4. The Director shall cooperate with the Office of Economic Development in carrying out the provisions of this section.
5. The Director shall submit to the Office of Economic Development an annual report, at such a time and containing such information as the Office may require, regarding the partial abatements granted pursuant to this section.
6. The provisions of subparagraph (4) of paragraph (d) of subsection 1 and subparagraph (4) of paragraph (e) of subsection 1 concerning the average hourly wage of the employees working on the construction of a facility do not apply to the wages of an apprentice as that term is defined in NRS 610.010.
7. As used in this section, "wage" or "wages":
(a) Means:
(1) The basic hourly rate of pay; and
(2) The amount of any hourly contribution made to a third-party administrator pursuant to a pension plan or vacation plan which is for the benefit of the employee.
(b) Except as otherwise provided in paragraph (a), does not include the amount of any health insurance plan, pension or other bona fide fringe benefits which are a benefit to the employee.
(Added to NRS by 2009, 2004; A 2011, 2071, 3479; 2013, 3203, 3501; 2013, 27th Special Session, 27; 2017, 3814; 2019, 1180; 2021, 3775)

1. The Director, in consultation with the Office of Economic Development, shall approve an application for a partial abatement pursuant to NRS 701A.300 to 701A.390, inclusive, if the Director, in consultation with the Office of Economic Development, makes the following determinations:
(a) The applicant has executed an agreement with the Director which must:
(1) State that the facility will, after the date on which a certificate of eligibility for the abatement is issued pursuant to NRS 701A.370, continue in operation in this State for a period specified by the Director, which must be at least 10 years, and will continue to meet the eligibility requirements for the abatement; and
(2) Bind the successors in interest in the facility for the specified period.
(b) The facility is registered pursuant to the laws of this State or the applicant commits to obtain a valid business license and all other permits required by the county, city or town in which the facility operates.
(c) No funding is or will be provided by any governmental entity in this State for the acquisition, design or construction of the facility or for the acquisition of any land therefor, except any private activity bonds as defined in 26 U.S.C. § 141.
(d) Except as otherwise provided in paragraph (e), if the facility will be located in a county whose population is 100,000 or more or a city whose population is 60,000 or more, the facility meets the following requirements:
(1) There will be 75 or more full-time employees working on the construction of the facility during the second quarter of construction, including, unless waived by the Director for good cause, at least 50 percent who are residents of Nevada;
(2) Establishing the facility will require the facility to make a capital investment of at least $10,000,000 in this State;
(3) The average hourly wage that will be paid by the facility to its employees in this State is at least 110 percent of the average statewide hourly wage, excluding management and administrative employees, as established by the Employment Security Division of the Department of Employment, Training and Rehabilitation on July 1 of each fiscal year; and
(4) Except as otherwise provided in subsection 6, the average hourly wage of the employees working on the construction of the facility will be at least 175 percent of the average statewide hourly wage, excluding management and administrative employees, as established by the Employment Security Division of the Department of Employment, Training and Rehabilitation on July 1 of each fiscal year and:
(I) The employees working on the construction of the facility must be provided a health insurance plan that is provided by a third-party administrator and includes health insurance coverage for dependents of the employees; and
(II) The cost of the benefits provided to the employees working on the construction of the facility will meet the minimum requirements for benefits established by the Director by regulation pursuant to NRS 701A.390.
(e) If the facility will be located in a county whose population is less than 100,000, in an area of a county whose population is 100,000 or more that is located within the geographic boundaries of an area that is designated as rural by the United States Department of Agriculture and at least 20 miles outside of the geographic boundaries of an area designated as urban by the United States Department of Agriculture, or in a city whose population is less than 60,000, the facility meets the following requirements:
(1) There will be 50 or more full-time employees working on the construction of the facility during the second quarter of construction, including, unless waived by the Director for good cause, at least 50 percent who are residents of Nevada;
(2) Establishing the facility will require the facility to make a capital investment of at least $3,000,000 in this State;
(3) The average hourly wage that will be paid by the facility to its employees in this State is at least 110 percent of the average statewide hourly wage, excluding management and administrative employees, as established by the Employment Security Division of the Department of Employment, Training and Rehabilitation on July 1 of each fiscal year; and
(4) Except as otherwise provided in subsection 6, the average hourly wage of the employees working on the construction of the facility will be at least 175 percent of the average statewide hourly wage, excluding management and administrative employees, as established by the Employment Security Division of the Department of Employment, Training and Rehabilitation on July 1 of each fiscal year and:
(I) The employees working on the construction of the facility must be provided a health insurance plan that is provided by a third-party administrator and includes health insurance coverage for dependents of the employees; and
(II) The cost of the benefits provided to the employees working on the construction of the facility will meet the minimum requirements for benefits established by the Director by regulation pursuant to NRS 701A.390.
(f) The financial benefits that will result to this State from the employment by the facility of the residents of this State and from capital investments by the facility in this State will exceed the loss of tax revenue that will result from the abatement.
(g) The facility is consistent with the State Plan for Economic Development developed by the Executive Director of the Office of Economic Development pursuant to subsection 2 of NRS 231.053.
2. The Director shall not approve an application for a partial abatement of the taxes imposed pursuant to chapter 361 of NRS submitted pursuant to NRS 701A.360 by a facility for the generation of process heat from solar renewable energy, a wholesale facility for the generation of electricity from renewable energy, a facility for the storage of energy from renewable generation or a hybrid renewable generation and energy storage facility unless the application is approved or deemed approved pursuant to this subsection. The board of county commissioners of a county must provide notice to the Director that the board intends to consider an application and, if such notice is given, must approve or deny the application not later than 30 days after the board receives a copy of the application. The board of county commissioners:
(a) Shall, in considering an application pursuant to this subsection, make a recommendation to the Director regarding the application;
(b) May, in considering an application pursuant to this subsection, deny an application only if the board of county commissioners determines, based on relevant information, that:
(1) The projected cost of the services that the local government is required to provide to the facility will exceed the amount of tax revenue that the local government is projected to receive as a result of the abatement; or
(2) The projected financial benefits that will result to the county from the employment by the facility of the residents of this State and from capital investments by the facility in the county will not exceed the projected loss of tax revenue that will result from the abatement;
(c) Must not condition the approval of the application on a requirement that the facility agree to purchase, lease or otherwise acquire in its own name or on behalf of the county any infrastructure, equipment, facilities or other property in the county that is not directly related to or otherwise necessary for the construction and operation of the facility; and
(d) May, without regard to whether the board has provided notice to the Director of its intent to consider the application, make a recommendation to the Director regarding the application.
If the board of county commissioners does not approve or deny the application within 30 days after the board receives from the Director a copy of the application, the application shall be deemed approved.
3. Notwithstanding the provisions of subsection 1, the Director, in consultation with the Office of Economic Development, may, if the Director, in consultation with the Office, determines that such action is necessary:
(a) Approve an application for a partial abatement for a facility that does not meet any requirement set forth in subparagraph (1) or (2) of paragraph (d) of subsection 1 or subparagraph (1) or (2) of paragraph (e) of subsection 1; or
(b) Add additional requirements that a facility must meet to qualify for a partial abatement.
4. The Director shall cooperate with the Office of Economic Development in carrying out the provisions of this section.
5. The Director shall submit to the Office of Economic Development an annual report, at such a time and containing such information as the Office may require, regarding the partial abatements granted pursuant to this section.
6. The provisions of subparagraph (4) of paragraph (d) of subsection 1 and subparagraph (4) of paragraph (e) of subsection 1 concerning the average hourly wage of the employees working on the construction of a facility do not apply to the wages of an apprentice as that term is defined in NRS 610.010.
7. As used in this section, "wage" or "wages":
(a) Means:
(1) The basic hourly rate of pay; and
(2) The amount of any hourly contribution made to a third-party administrator pursuant to a pension plan or vacation plan which is for the benefit of the employee.
(b) Except as otherwise provided in paragraph (a), does not include the amount of any health insurance plan, pension or other bona fide fringe benefits which are a benefit to the employee.
(Added to NRS by 2009, 2004, 2010; A 2011, 2071, 3479; 2013, 3203, 3501; 2013, 27th Special Session, 27; 2017, 3814; 2019, 1180; 2021; 3775, effective July 1, 2032)

Structure Nevada Revised Statutes

Nevada Revised Statutes

Chapter 701A - Energy-Related Tax Incentives

NRS 701A.100 - Adoption of Green Building Rating System; requirements and limitations. [Effective through June 30, 2035.]

NRS 701A.110 - Partial abatement of certain property taxes for buildings or structures that meet certain standards under Green Building Rating System; requirements and limitations; regulations. [Effective through June 30, 2035.]

NRS 701A.200 - Exemption from certain property taxes for qualified energy systems: Requirements and limitations; regulations.

NRS 701A.210 - Partial abatement of certain property taxes for businesses and facilities using recycled material: Requirements and limitations.

NRS 701A.300 - Definitions. [Effective through June 30, 2049.]

NRS 701A.305 - "Biomass" defined. [Effective through June 30, 2049.]

NRS 701A.315 - "Director" defined. [Effective through June 30, 2049.]

NRS 701A.317 - "Energy storage technology" defined. [Effective through June 30, 2049.]

NRS 701A.320 - "Facility for the generation of electricity from renewable energy" defined. [Effective through June 30, 2049.]

NRS 701A.325 - "Facility for the generation of process heat from solar renewable energy" defined. [Effective through June 30, 2049.]

NRS 701A.327 - "Facility for the storage of energy from renewable generation" defined. [Effective through June 30, 2049.]

NRS 701A.330 - "Fuel cell" defined. [Effective through June 30, 2049.]

NRS 701A.333 - "Hybrid renewable generation and energy storage facility" defined. [Effective through June 30, 2049.]

NRS 701A.335 - "Local sales and use taxes" defined. [Effective through June 30, 2049.]

NRS 701A.340 - "Renewable energy" defined. [Effective through June 30, 2049.]

NRS 701A.345 - "Wholesale facility for the generation of electricity from renewable energy" defined. [Effective through June 30, 2049.]

NRS 701A.360 - Application for partial abatement; ineligible facilities; required notices; public hearing on application. [Effective through June 30, 2049.]

NRS 701A.365 - Requirements for approval of application; exceptions; submission of annual report to Office of Economic Development. [Effective through June 30, 2032.] Requirements for approval of application; exceptions; submission of annual report t...

NRS 701A.370 - Duration, amount and other terms of partial abatement; notice of abatement; distribution of certificate of eligibility by Director. [Effective through June 30, 2049.]

NRS 701A.375 - Publication of fiscal notes; distribution of certificate of eligibility by Department of Taxation. [Effective through June 30, 2049.]

NRS 701A.377 - Recipient required to maintain certain records regarding employees. [Effective through June 30, 2049.]

NRS 701A.379 - Recipient required to submit annual payroll report; form; contents. [Effective through June 30, 2049.]

NRS 701A.380 - Termination of partial abatement for noncompliance; opportunity to cure noncompliance; required notices; repayment of taxes after termination. [Effective through June 30, 2049.]

NRS 701A.385 - Allocation of certain taxes collected from facilities receiving partial abatement. [Effective through June 30, 2049.]

NRS 701A.390 - Regulations; Director authorized to charge and collect fee for application for partial abatement. [Effective through June 30, 2049.]

NRS 701A.450 - Creation; administration; interest and income; use of money; nonreversion; agreement for repayment of certain loans or distributions through payroll deductions; regulations. [Effective through June 30, 2049.]