90-6-308. Permit procedure and review of impact plan to run concurrently. It is intended that the procedure for fulfilling the permit requirement of 82-4-335 and the review of the impact plan by the board under 90-6-307(5) and (6), if review occurs, are to run concurrently.
History: En. Sec. 9, Ch. 617, L. 1981; amd. Sec. 4, Ch. 311, L. 1987.
Structure Montana Code Annotated
Title 90. Planning, Research, and Development
Chapter 6. Community Impact -- Planning and Abatement
Part 3. Hard-Rock Mining Impact
90-6-301. Declaration of necessity and purpose
90-6-303. Presiding officer -- meetings -- facilities -- funding
90-6-304. Accounts established
90-6-305. Hard-rock mining impact board -- general powers
90-6-307. Impact plan to be submitted
90-6-308. Permit procedure and review of impact plan to run concurrently
90-6-309. Tax prepayment -- large-scale mineral development
90-6-310. Local government facility impact bonds
90-6-311. Impact plan amendments
90-6-312. through 90-6-320 reserved
90-6-323. Local government budget authority