85-15-213. Periodic inspections after construction. (1) (a) A high-hazard dam, whether or not previously permitted by the department, must be inspected as often as considered necessary by the department, but at least once every 5 years, in order to ensure the continued safe operation of the high-hazard dam.
(b) The department determination that an inspection is necessary more often than once every 5 years, as provided in subsection (1)(a), must be based on substantive evidence, and the reasons for that determination must be stated in writing.
(2) Periodic inspections required by this section must be performed by a qualified engineer, who shall make a report of the inspection to the department. If the department finds that the high-hazard dam conforms to current safety standards, it shall issue or reissue, as the case may be, a permit to continue operation of the high-hazard dam, containing conditions on the safe operation of the high-hazard dam as it considers necessary.
(3) The owner is responsible for inspections required under this section.
History: En. Sec. 10, Ch. 501, L. 1985; amd. Sec. 6, Ch. 418, L. 1993.
Structure Montana Code Annotated
Part 2. Construction, Inspection, and Repair of Dams
85-15-201. Renumbered 85-15-306
85-15-202. Renumbered 85-15-307
85-15-203. Renumbered 85-15-308
85-15-204. Renumbered 85-15-309
85-15-205. Renumbered 85-15-310
85-15-206. Renumbered 85-15-311
85-15-207. Dams and reservoirs -- how constructed
85-15-208. Construction in a secure manner
85-15-209. High-hazard dam -- determination
85-15-210. Preparation and approval of plans
85-15-211. Inspection and reports during construction
85-15-213. Periodic inspections after construction
85-15-214. Requested inspections -- costs -- limitations against unsafe structures