69-4-313. Cost and feasibility report. (1) The public utility report shall set forth an estimate of the total underground conversion costs and shall also indicate the costs of underground conversion of facilities of the public utility located within the boundaries of the various parcels or lots then receiving service. The report shall also contain the public utility's recommendations concerning the feasibility of the project for the district proposed, insofar as the physical characteristics of the district are concerned. The report shall make recommendations by the public utility concerning inclusion or exclusion of areas within the district or immediately adjacent to the district.
(2) The governing body shall give careful consideration to the public utility's recommendations concerning feasibility, recognizing their expertise in this area, and may amend the boundaries of the proposed improvement district; provided, that the costs and feasibility report of the public utility contains a cost figure on the district as amended, or it may request a new cost and feasibility report from the public utility concerned on the basis of the amended district. Should a delay result in a significant increase of the estimated conversion costs, new hearings shall be held on the creation of the district. In the event an increase of 10% or less results from delay, only the hearing on the assessments need be held again.
History: En. Sec. 7, Ch. 429, L. 1971; R.C.M. 1947, 70-607.
Structure Montana Code Annotated
Title 69. Public Utilities and Carriers
Chapter 4. Utility Lines and Facilities
Part 3. Underground Conversion of Utilities
69-4-302. Statement of findings and purpose
69-4-304. Exclusion for high-voltage transmission lines
69-4-305. Effect on authority of public service commission
69-4-306. through 69-4-310 reserved
69-4-311. Authorization to create special improvement districts
69-4-312. Procedure to initiate creation of district -- resolution for feasibility study
69-4-313. Cost and feasibility report
69-4-314. Determination of conversion costs
69-4-334. through 69-4-350 reserved
69-4-351. Maintenance and construction of converted facilities
69-4-352. Title to converted facilities
69-4-353. Conversion of facilities on public property -- notice to landowners
69-4-354. Conversion of facilities on private property
69-4-355. Procedure upon failure to effect conversion on private property
69-4-356. Payment of public utility
69-4-357. Prohibition on reinstallation of overhead facilities
69-4-358. Postponement of conversion until certain actions occur