Section 324.63707 - Fifteen-Year Mining Plan; Submission of Duplicate Copy of Cell-Unit Mining and Reclamation Plan.

Sec. 63707.
(1) The 15-year mining plan shall include the following:
(a) The location and acreage of sand dune areas presently being mined and the amount of sand being mined.
(b) The location and acreage of sand dune areas not presently being mined but planned for that purpose and the amount of sand planned to be mined.
(c) A schedule indicating when the mining activity will begin in each sand dune area and the probable termination date of mining activities in each area.
(d) Additional information requested by the department.
(2) A duplicate copy of the cell-unit mining and reclamation plan shall be submitted to the soil conservation district in the county where the mining activity is proposed to occur. The soil conservation district shall have 30 days after receipt of the plan to review the proposal and submit written comments to the department.
History: Add. 1995, Act 57, Imd. Eff. May 24, 1995 Popular Name: Act 451Popular Name: NREPA

Structure Michigan Compiled Laws

Michigan Compiled Laws

Chapter 324 - Natural Resources and Environmental Protection

Act 451 of 1994 - Natural Resources and Environmental Protection Act (324.101 - 324.90106)

Article III - Natural Resources Management (324.30101...324.83109)

451-1994-III-3 - Chapter 3 Management of Nonrenewable Resources (324.60101...324.64111)

451-1994-III-3-4 - Subchapter 4 Mineral Mining (324.63101...324.63714)

451-1994-III-3-4-637 - Part 637 Sand Dune Mining (324.63701...324.63714)

Section 324.63701 - Definitions.

Section 324.63702 - Sand Dune Mining Permit Within Critical Dune Area; “Adjacent” Defined.

Section 324.63703 - Great Lakes Sand Dune Areas; Comprehensive Study and Inventory.

Section 324.63704 - Sand Dune Mining; Permit; Requirements.

Section 324.63705 - Environmental Impact Statement.

Section 324.63706 - Progressive Cell-Unit Mining and Reclamation Plan; Sand Dune Mining Permit; Requirements.

Section 324.63707 - Fifteen-Year Mining Plan; Submission of Duplicate Copy of Cell-Unit Mining and Reclamation Plan.

Section 324.63708 - Sand Dune Mining Permit; Duration; Renewal; Contents; Reasons for Permitting Removal of Barrier Dune; List of Pending Applications.

Section 324.63709 - Denial of Sand Dune Mining Permit.

Section 324.63710 - Extraction of Sand or Other Minerals by State.

Section 324.63711 - Assessment of Fee for Surveillance, Monitoring, Administration, and Enforcement of Part; Disposition of Unexpended Fees; Annual Report of Operator; Confidentiality; Failure to Submit Annual Report; Penalty for Unpaid Fee; Records;...

Section 324.63712 - Conformance Bond; Reclassification of Active Cell-Unit to Interim Cell-Unit; Notice of Completion or Acceptance of Reclamation Activity; Compliance or Approval Required for Mining or Extraction; Violation as Grounds for Revocation...

Section 324.63713 - Rules.

Section 324.63714 - Suspension or Revocation of Permit; Restraining Order, Injunction, or Other Appropriate Remedy; Violation as Misdemeanor; Penalty.