(a) Within 30 days after the first meeting of the Commission after submission of a completed application, the Commission shall notify an applicant in writing:
(1) whether the application for a license is approved or denied; and
(2) of the reasons for denial, if the application is denied.
(b) (1) If the application is denied, the applicant, within 10 days after the notice of denial is mailed, may request a hearing.
(2) The hearing shall be held in accordance with § 8-312 of this subtitle within 30 days after the date that the Commission receives the request.
(3) The Commission shall make a decision within a reasonable time, but not later than 60 days after the hearing.
Structure Maryland Statutes
Section 8-301 - License Required; Exceptions
Section 8-302.1 - Contractor License -- Liability Insurance
Section 8-302.2 - Contractor License -- Qualifications of Applicants
Section 8-303 - Applications for Licenses
Section 8-305 - Approval or Denial of License
Section 8-306 - Issuance of License
Section 8-307 - Scope of License
Section 8-308 - Term and Renewal of License; Notice of Cancellation
Section 8-308.1 - Inactive Status
Section 8-309 - Change of Information
Section 8-310 - Relationship of Salespersons and Contractors
Section 8-311 - Denials, Reprimands, Suspensions, and Revocations -- Grounds; Penalty
Section 8-312 - Denials, Reprimands, Suspensions, and Revocations -- Hearings
Section 8-313 - Home Improvement Hearing Board
Section 8-314 - Judicial Review
Section 8-315 - Payment of Compensation; Effect of Loss of License
Section 8-316 - Reapplication for License; Reinstatement of License