(a)    Except as provided in subsection (c) of this section, Cecil County shall obtain the following by a competitively bid contract awarded to the lowest responsive and responsible bidder:
        (1)    the building or repair of a bridge; and
        (2)    the purchase or lease of bridge construction equipment or machinery.
    (b)    (1)    The governing body of Cecil County shall advertise for bids on a contract under subsection (a) of this section in at least one newspaper of general circulation in the county.
        (2)    The advertisement shall:
            (i)    appear at least once;
            (ii)    appear at least 1 week, but not more than 30 days, before the final date for submitting bids;
            (iii)    if the contract relates to building or repair of a bridge, specify the location where the bridge is to be built or repaired;
            (iv)    include a description of the goods or services required under the contract;
            (v)    state that sealed bids for goods or services will be received until the date designated in the advertisement; and
            (vi)    designate a date for the opening of the bids.
    (c)    (1)    Subsections (a) and (b) of this section do not apply to an expenditure that:
            (i)    is $10,000 or less; or
            (ii)    the governing body of Cecil County by a recorded majority vote taken at a public meeting declares to be an emergency expenditure.
        (2)    For an expenditure under this subsection, the governing body may determine:
            (i)    the manner of providing for the expenditure; and
            (ii)    if the building or repair is by contract, the manner in which the contract is awarded.
    (d)    (1)    A contract entered into in violation of subsection (a) or (b) of this section is void, unless:
            (i)    a court determines in a judicial action that all parties acted in good faith; and
            (ii)    the parties have substantially complied with the provisions of subsections (a) and (b) of this section.
        (2)    If a contract is void under this subsection, the governing body of Cecil County shall compensate the contractor for costs actually incurred if the contractor:
            (i)    acted in good faith;
            (ii)    did not directly contribute to the violation; and
            (iii)    did not know of the violation.
    (e)    A person who willfully violates this section is guilty of a misdemeanor and on conviction is subject to a fine not exceeding $1,000.