§1116. Design standards
All new dams that reasonably will be classified as high or significant hazard potential dams must be designed, constructed or reconstructed under the supervision of a registered professional engineer. Prior to construction, the dam owner shall provide a copy of the plans and specifications to the department. [PL 2001, c. 460, §3 (NEW).]
SECTION HISTORY
PL 2001, c. 460, §3 (NEW).
Structure Maine Revised Statutes
TITLE 37-B: DEFENSE, VETERANS AND EMERGENCY MANAGEMENT
37-B §1113. Duties of the department
37-B §1114. Powers of the department
37-B §1117. Inspectors of dams
37-B §1118. Dam hazard evaluation
37-B §1119. Dam condition inspection
37-B §1125. Relief of obligation
37-B §1126. Access and notification
37-B §1127. Emergency action plans
37-B §1128. Notice of transfer of ownership