Section 573.28 - Early release of retained funds.

573.28 Early release of retained funds.
1. For purposes of this section:
a. “Authorized contract representative” means the person chosen by the governmental entity or the department to represent its interests or the person designated in the contract as the party representing the governmental entity’s or the department’s interest regarding administration and oversight of the project.
b. “Department” means the state department of transportation.
c. “Governmental entity” means the state, political subdivisions of the state, public school corporations, and all officers, boards, or commissions empowered by law to enter into contracts for the construction of public improvements, excluding the state board of regents and the department.
d. “Public improvement” means a building or construction work which is constructed under the control of a governmental entity and is paid for in whole or in part with funds of the governmental entity, including a building or improvement constructed or operated jointly with any other public or private agency, but excluding urban renewal demolition and low-rent housing projects, industrial aid projects authorized under chapter 419, emergency work or repair or maintenance work performed by employees of a governmental entity, and excluding a highway, bridge, or culvert project, and excluding construction or repair or maintenance work performed for a city utility under chapter 388 by its employees or performed for a rural water district under chapter 357A by its employees.
e. “Repair or maintenance work” means the preservation of a building, storm sewer, sanitary sewer, or other public facility or structure so that it remains in sound or proper condition, including minor replacements and additions as necessary to restore the public facility or structure to its original condition with the same design.
f. “Substantially completed” means the first date on which any of the following occurs:
(1) Completion of the public improvement project or the highway, bridge, or culvert project or when the work on the public improvement or the highway, bridge, or culvert project has been substantially completed in general accordance with the terms and provisions of the contract.
(2) The work on the public improvement or on the designated portion is substantially completed in general accordance with the terms of the contract so that the governmental entity or the department can occupy or utilize the public improvement or designated portion of the public improvement for its intended purpose. This subparagraph shall not apply to highway, bridge, or culvert projects.
(3) The public improvement project or the highway, bridge, or culvert project is certified as having been substantially completed by either of the following:
(a) The architect or engineer authorized to make such certification.
(b) The authorized contract representative.
(4) The governmental entity or the department is occupying or utilizing the public improvement for its intended purpose. This subparagraph shall not apply to highway, bridge, or culvert projects.
2. Payments made by a governmental entity or the department for the construction of public improvements and highway, bridge, or culvert projects shall be made in accordance with the provisions of this chapter, except as provided in this section:
a. At any time after all or any part of the work on the public improvement or highway, bridge, or culvert project is substantially completed, the contractor may request the release of all or part of the retained funds owed. The request shall be accompanied by a sworn statement of the contractor that, ten calendar days prior to filing the request, notice was given as required by paragraphs “f” and “g” to all known subcontractors, sub-subcontractors, and suppliers.
b. Except as provided under paragraph “c”, upon receipt of the request, the governmental entity or the department shall release all or part of the retained funds. Retained funds that are approved as payable shall be paid at the time of the next monthly payment or within thirty days, whichever is sooner. If partial retained funds are released pursuant to a contractor’s request, no retained funds shall be subsequently held based on that portion of the work. If within thirty days of when payment becomes due the governmental entity or the department does not release the retained funds due, interest shall accrue on the amount of retained funds at the rate of interest that is calculated as the prime rate plus one percent per year as of the day interest begins to accrue until the amount is paid.
c. If labor and materials are yet to be provided at the time the request for the release of the retained funds is made, an amount equal to two hundred percent of the value of the labor or materials yet to be provided, as determined by the governmental entity’s or the department’s authorized contract representative, may be withheld until such labor or materials are provided.
d. An itemization of the labor or materials yet to be provided, or the reason that the request for release of retained funds is denied, shall be provided to the contractor in writing within thirty calendar days of the receipt of the request for release of retained funds.
e. The contractor shall release retained funds to the subcontractor or subcontractors in the same manner as retained funds are released to the contractor by the governmental entity or the department. Each subcontractor shall pass through to each lower-tier subcontractor all retained fund payments from the contractor.
f. Prior to applying for release of retained funds, the contractor shall send a notice to all known subcontractors, sub-subcontractors, and suppliers that provided labor or materials for the public improvement project or the highway, bridge, or culvert project.
g. The notice shall be substantially similar to the following:
NOTICE OF CONTRACTOR’S REQUEST
FOR EARLY RELEASE OF RETAINED FUNDS
You are hereby notified that [name of contractor] will be requesting an early release of funds on a public improvement project or a highway, bridge, or culvert project designated as [name of project] for which you have or may have provided labor or materials. The request will be made pursuant to Iowa Code section 573.28. The request may be filed with the [name of governmental entity or department] after ten calendar days from the date of this notice. The purpose of the request is to have [name of governmental entity or department] release and pay funds for all work that has been performed and charged to [name of governmental entity or department] as of the date of this notice. This notice is provided in accordance with Iowa Code section 573.28.
2018 Acts, ch 1097, §5
Referred to in §573.15

Structure Iowa Code

Iowa Code

Title XIV - PROPERTY

Chapter 573 - LABOR AND MATERIAL ON PUBLIC IMPROVEMENTS

Section 573.1 - Definitions.

Section 573.2 - Public improvements — bond — waiver and remedies.

Section 573.3 - Bond mandatory.

Section 573.4 - Deposit in lieu of bond.

Section 573.5 - Amount of bond.

Section 573.6 - Subcontractors on public improvements.

Section 573.7 - Claims for material or labor.

Section 573.8 - Highway improvements.

Section 573.9 - Officer to endorse time of filing claim.

Section 573.10 - Time of filing claims.

Section 573.11 - Claims filed after action brought.

Section 573.12 - Payments and retention from payments on contracts.

Section 573.13 - Inviolability and disposition of fund.

Section 573.14 - Retention of unpaid funds.

Section 573.15 - Claim against retainage or bond.

Section 573.15A - Early release of retained funds.

Section 573.16 - Optional and mandatory actions — bond to release.

Section 573.17 - Parties.

Section 573.18 - Adjudication — payment of claims.

Section 573.19 - Insufficiency of funds.

Section 573.20 - Converting property into money.

Section 573.21 - Attorney fees.

Section 573.22 - Unpaid claimants — judgment on bond.

Section 573.23 - Abandonment of public work — effect.

Section 573.24 - Notice of claims to state department of transportation.

Section 573.25 - Filing of claim — effect.

Section 573.26 - Public corporation — action on bond.

Section 573.27 - Payment before work completed.

Section 573.28 - Early release of retained funds.