Sec. 0.5. (a) The definitions in IC 5-16-13 apply to this section.
(b) For purposes of IC 5-16-13-10(c) and this section, a contractor must be qualified under this chapter before doing any work on a public works project that is the construction, improvement, alteration, repair, or maintenance of a highway, street, or road (as defined by IC 8-23-1-23) or alley.
(c) Notwithstanding the applicability date specified in IC 5-16-13-10(c) and subject to subsection (d), the requirement that a contractor must be qualified under this chapter before doing any work on a public works project applies to a public works contract awarded after December 31, 2016.
(d) This subsection applies to a public works project awarded after December 31, 2016, by a local unit. A contractor in any contractor tier is not required to be qualified under this chapter before doing any work on a public works project awarded by a local unit whenever:
(1) the total amount of the contract awarded to the contractor for work on the public works project is less than three hundred thousand dollars ($300,000); and
(2) the local unit complies with IC 36-1-12 in awarding the contract for the public works project.
As added by P.L.144-2016, SEC.3. Amended by P.L.85-2017, SEC.39.
Structure Indiana Code
Title 8. Utilities and Transportation
Article 23. Indiana Department of Transportation
Chapter 10. Qualifications of Bidders for Contracts
8-23-10-0.1. Application of Certain Amendments to Chapter
8-23-10-1. Qualified Bidders Required; Exception
8-23-10-2.5. Public Availability of Certificates of Qualification
8-23-10-3. Financial Statements of Applicants
8-23-10-4. Subcontractors; Qualification
8-23-10-5. Notice of Action on Application; Reapplication