Indiana Code
Chapter 8.9. Financing of Substitute Natural Gas Costs
8-1-8.9-11. Qualified Order for Cost Recovery

Sec. 11. (a) Notwithstanding any other law, the commission may, in accordance with this chapter and IC 8-1-2-42.1, issue a qualified order that:
(1) approves the terms of a qualified contract; and
(2) authorizes the recovery of qualified costs by an energy utility from its customers.
(b) A qualified order issued under this section may not be:
(1) rescinded;
(2) nullified; or
(3) modified;
in such a manner that reduces or otherwise impairs the value of an SNG property interest.
As added by P.L.175-2007, SEC.21.