Indiana Code
Chapter 8.5. Electric Utility Resource Planning and Certification
8-1-8.5-6. Review of Construction; Force and Effect of Certificate Approved Under Review; Election to Defer Review

Sec. 6. (a) In addition to the review of the continuing need for the facility under construction prescribed in section 5.5 of this chapter, the commission shall, at the request of the public utility, maintain an ongoing review of such construction as it proceeds. The applicant shall submit each year during construction, or at such other periods as the commission and the public utility mutually agree, a progress report and any revisions in the cost estimates for the construction.
(b) If the commission approves the construction and the cost of the portion of the facility under review, the certificate shall remain in full force and effect.
(c) If the commission disapproves of all or part of the construction or cost of the portion of the facility under review, the commission may modify or revoke the certificate.
(d) Alternatively, the public utility may elect to forego commission review under subsection (a) and defer the review of the construction and cost until completion or cancellation of the facility.
As added by P.L.43-1983, SEC.12. Amended by P.L.88-1985, SEC.12; P.L.53-1992, SEC.6.

Structure Indiana Code

Indiana Code

Title 8. Utilities and Transportation

Article 1. Utilities Generally

Chapter 8.5. Electric Utility Resource Planning and Certification

8-1-8.5-1. Definitions

8-1-8.5-2. Necessity for Certification

8-1-8.5-3. Analysis of Needs; Integrated Resource Plans; Hearings; Report

8-1-8.5-3.2. Integrated Resources Plans Submitted After June 30, 2021, and Before January 1, 2025; Commission to Evaluate Impact of Federal Phaseout Mandates on Estimated Useful Life of Existing and Proposed Generating Facilities

8-1-8.5-3.5. Forecasting Group

8-1-8.5-4. Consideration of Petition; Petition for Construction of New Generating Facility Submitted After June 30, 2021, and Before January 1, 2025; Commission to Consider Impact of Federal Phaseout Mandates on Estimated Useful Life of Proposed Faci...

8-1-8.5-5. Estimate of Costs; Hearing on Application; Granting of Certificate; Findings; Utility Specific Proposals; Construction of Large Generating Facilities; Competitive Bidding

8-1-8.5-5.5. Review of Continuing Need; Modification or Revocation of Certificate

8-1-8.5-6. Review of Construction; Force and Effect of Certificate Approved Under Review; Election to Defer Review

8-1-8.5-6.5. Rates; Recovery of Costs

8-1-8.5-7. Exemptions From Certification Requirements; Report to Commission of Proposed Construction Required

8-1-8.5-8. Construction of Chapter; Valuation of Property

8-1-8.5-9. Energy Efficiency Programs; Opt Out by Industrial Customers; Prohibition Against Extending or Renewing Energy Efficiency Programs Established Under Dsm Order

8-1-8.5-10. Energy Efficiency Goals and Programs; Evaluation, Measurement, and Verification; Recovery of Program Costs; Opt Out by Industrial Customers

8-1-8.5-12. Coal Transition Workers; Priority for Awarding High Value Workforce Ready Credit-Bearing Grants

8-1-8.5-12.1. "Small Modular Nuclear Reactor"; Commission to Adopt Rules Concerning the Granting of Certificates for Small Modular Reactors; Requirements for Commission's Rules

8-1-8.5-13. Legislative Findings; Definitions; Public Utilities' Annual Resource Planning Report to Commission; Three-Year Forecast; Contents; Commission's Review; Order to Acquire or Construct Resources