Indiana Code
Chapter 28. Water Utility Environmental Compliance Plans
8-1-28-8. Rejection of Plan; Modified Plan; Withdrawal of Plan Without Prejudice

Sec. 8. (a) If the commission finds that an environmental compliance plan submitted by a public utility does not satisfy the requirements of section 7 of this chapter, the commission may reject the plan.
(b) If the public utility's environmental compliance plan is rejected by the commission, the public utility may voluntarily submit to the commission a modified plan intended to satisfy the requirements of section 7 of this chapter.
(c) A modified plan submitted under subsection (b) shall be considered by the commission under sections 6 and 7 of this chapter.
(d) A public utility may withdraw a proposed environmental compliance plan without prejudice.
As added by P.L.76-1991, SEC.2.

Structure Indiana Code

Indiana Code

Title 8. Utilities and Transportation

Article 1. Utilities Generally

Chapter 28. Water Utility Environmental Compliance Plans

8-1-28-1. "Clean Water Act" Defined

8-1-28-2. "Environmental Compliance Plan" Defined

8-1-28-3. "Public Utility" Defined

8-1-28-4. "Safe Drinking Water Act" Defined

8-1-28-5. Submission of Plan to Commission; Required Information

8-1-28-6. Public Hearing on Plan; Notice

8-1-28-7. Order Approving Plan; Conditions

8-1-28-8. Rejection of Plan; Modified Plan; Withdrawal of Plan Without Prejudice

8-1-28-9. Submission of Plan to Government Environmental Agency; Conflicts

8-1-28-10. Modification of Previously Approved Plan; Review by Commission

8-1-28-11. Recovery of Costs by Public Utility for Capital Projects or Implemented Plan

8-1-28-12. Revised Cost and Schedule Estimate for Developing and Implementing Plan; Submission to Commission

8-1-28-13. Utility's Recovery of Expenditures as Result of Plan Modification

8-1-28-14. Recovery of Costs Incurred by Utility in Implementing Measure Set Forth in Plan but Disapproved by Commission Upon Review

8-1-28-15. Review of Plan by Commission; Withdrawal of Approval or Modification of Plan

8-1-28-16. Ongoing Review of Cost and Implementation of Plan; Progress Report; Recovery of Costs; Final Approval by Commission

8-1-28-17. Disapproval or Approval of All or Part of Plan; Effect

8-1-28-18. General Rate Proceedings; Consideration of Change in Risk to Utility Following Approval of Plan

8-1-28-19. Voluntary Nature of Chapter Procedure