Sec. 2. (a) A first tier subcontract shall be awarded to the bidder for that contract that would be awarded the contract under the applicable contract award standard.
(b) Before award of a first tier subcontract, the CMc may prequalify potential bidders based on written criteria established and published by the public agency. Otherwise, the applicable public works statute applies.
As added by P.L.128-2014, SEC.1.
Structure Indiana Code
Title 5. State and Local Administration
Article 32. Employment of Construction Managers as Constructors for Projects
Chapter 5. Cmc Award of First Tier Subcontracts
5-32-5-1. Cmc Must Comply With Applicable Public Works Statute in Award of First Tier Subcontracts
5-32-5-2. Award of First Tier Subcontracts; Prequalification of Potential Bidders
5-32-5-3. Information About Bidders Submitted With Bid