Sec. 7. (a) If any of the following occur, the public agency may proceed as described in subsection (b):
(1) The CMc contract is terminated under section 6 of this chapter.
(2) The public agency and the selected offeror are unable to reach agreement on a CMc contract.
(3) The selected offeror does not provide the required bonds as provided in the RFP or this article.
(b) If any of the events described in subsection (a)(1), (a)(2), or (a)(3) occur, the public agency may do any of the following:
(1) Negotiate a contract with another offeror.
(2) Award contracts and complete the project under any other applicable public works statute.
(3) Terminate the project.
As added by P.L.128-2014, SEC.1.
Structure Indiana Code
Title 5. State and Local Administration
Article 32. Employment of Construction Managers as Constructors for Projects
5-32-4-1. Negotiation of Cmc Contract Terms and Conditions
5-32-4-2. Cmc to Provide Payment and Performance Bonds; Construction May Not Proceed Without Bonds
5-32-4-3. Contract Provisions; Adjustment of Compensation, Other Incentives
5-32-4-4. Cost Overrun or Delay Damages; Early Completion Incentives
5-32-4-5. Changes to Cmc Contract
5-32-4-6. Termination of Cmc Contract
5-32-4-7. Public Agency Options if Cmc Contract Terminated or Not Executed