Sec. 8. (a) The contractor and each subcontractor engaged in installing energy conservation measures under a guaranteed energy savings contract shall keep full and accurate records indicating the names, classifications, and work performed by each worker employed by the respective contractor and subcontractor in connection with the work and an accurate record of the number of hours worked by each worker and the actual wages paid.
(b) The payroll records required to be kept under this section must be open to inspection by an authorized representative of the department and the department of labor.
As added by P.L.58-1999, SEC.9 and P.L.172-1999, SEC.8. Amended by P.L.252-2015, SEC.5.
Structure Indiana Code
Title 4. State Offices and Administration
Article 13.6. State Public Works
Chapter 8. Energy Cost Savings Contracts
4-13.6-8-2. "Energy Cost Savings Contract"
4-13.6-8-3. "Qualified Energy Savings Project"
4-13.6-8-4. "Qualified Provider"
4-13.6-8-5. Contract Proposals
4-13.6-8-6. Allowable Provisions in Contracts
4-13.6-8-7. Contract Approval and Guarantee
4-13.6-8-9. Reduction of State Appropriations Due to Energy Cost Savings Prohibited