Sec. 15. If a local governmental agency denies the emergency seawall or revetment permit, the local governmental agency shall provide the reasons for the denial in a single response to the person. A person may submit not more than one (1) completed reapplication for an emergency seawall or revetment permit that lists reasons why the local governmental agency should approve the person's emergency permit. Not later than ten (10) business days after the person submits the completed reapplication, a local governmental agency shall:
(1) approve; or
(2) deny;
the person's reapplication for the emergency permit. If a local governmental agency does not approve or deny the person's reapplication for the emergency seawall or revetment permit within ten (10) business days, the emergency permit is automatically approved and considered issued to the person.
As added by P.L.164-2020, SEC.64.
Structure Indiana Code
Chapter 29. Seawall and Revetment Permits
36-1-29-1. Application of Chapter; Location
36-1-29-2. Application of Chapter; Not Affected
36-1-29-4. "Local Governmental Agency"
36-1-29-5. "Ordinary High Water Mark"
36-1-29-10. Seawalls and Revetments; Repair; Construction; Temporary Structures
36-1-29-11. Repair of Existing Seawalls and Revetments
36-1-29-12. Construction of New Seawalls or Revetments
36-1-29-13. Contiguous Seawalls
36-1-29-14. Permits; Application and Approval
36-1-29-15. Denial of Permit by Local Governmental Agency; Reapplication