Sec. 17. (a) If a contractor determines that a subcontractor is in violation of this chapter, the contractor may terminate a contract with the subcontractor for the violation.
(b) The termination of a contract under subsection (a) for a violation of this chapter by a subcontractor may not be considered a breach of contract by the contractor or the subcontractor.
(c) A subcontractor may file an action with a circuit or superior court having jurisdiction in the county to challenge a termination of a contract under subsection (a) not later than twenty (20) days after the contractor terminates the contract with the subcontractor.
As added by P.L.171-2011, SEC.16. Amended by P.L.6-2012, SEC.158.
Structure Indiana Code
Article 5. Unlawful Labor Practices
Chapter 1.7. Public Contract for Services; Business Entities; Unauthorized Aliens
22-5-1.7-3. "E-Verify Program"
22-5-1.7-5. "Political Subdivision"
22-5-1.7-6. "Public Contract for Services"
22-5-1.7-6.4. "Public Works Project"
22-5-1.7-9. "Unauthorized Alien"
22-5-1.7-10. State Agencies and Political Subdivisions Required to Use E-Verify Program; Exception
22-5-1.7-11.1. Contractors With Public Works Contract Required to Use E-Verify Program
22-5-1.7-15. Certification by Subcontractor