Sec. 22. The commission shall determine the amount of a penalty bond subject to the following:
(1) A bond may not be less than:
(A) five thousand dollars ($5,000); or
(B) one thousand dollars ($1,000) per acre;
whichever is larger.
(2) The total bond may not be greater than five thousand dollars ($5,000) per acre.
[Pre-1995 Recodification Citation: 13-4-6-5(f) part.]
As added by P.L.1-1995, SEC.29.
Structure Indiana Code
Title 14. Natural and Cultural Resources
Chapter 1. Surface Mining Reclamation
14-36-1-1. Purpose of Reclamation
14-36-1-3. Operations Subject to Certain Statutes
14-36-1-4. "Affected Area" Defined
14-36-1-5. "Cast Overburden" Defined
14-36-1-7. "Mining Refuse" Defined
14-36-1-8. "Operation" Defined
14-36-1-10. "Overburden" Defined
14-36-1-11. "Reclamation" Defined
14-36-1-12. "Reclamation Plan" Defined
14-36-1-13. Commission's Powers Regarding Permits
14-36-1-14. Duties of Director
14-36-1-16. Permit Powers; Effective Date
14-36-1-17. Contents of Application
14-36-1-18. Maps Accompanying Application
14-36-1-19. Amendment of Information or Consent
14-36-1-24. Bond Without Surety
14-36-1-25. Increasing Acres for Permit
14-36-1-26. Reclamation Procedures
14-36-1-27. Report of Operation
14-36-1-28. Charge Against Bond; Release of Bond; Refund of Fees
14-36-1-29. Retention of Bond for Revegetation
14-36-1-31. Modification, Suspension, or Revocation of Permit
14-36-1-32. Applicability of Ic 4-21.5
14-36-1-33. Operator With Revoked Permit
14-36-1-34. Operator With Forfeited Bond