Sec. 6. (a) Notwithstanding the periods specified in sections 1 through 4 of this chapter and this section, a person proposing to construct, modify, or operate any equipment, facility, or pollution control device that is demonstrated to achieve pollution control or pollution prevention in excess of applicable federal, state, or local requirements may apply to the commissioner for an interim permit to construct, modify, or operate the equipment, facility, or pollution control device.
(b) The commissioner shall approve or deny the interim permit not later than sixty (60) days after receipt of the application for an interim permit, unless the applicant and the commissioner agree that a longer review period is necessary.
(c) This section does not relieve a person from complying with:
(1) the permit requirements provided under this title; and
(2) rules adopted under this title;
to the extent that this title and the rules are not inconsistent with this section.
[Pre-1996 Recodification Citation: 13-7-10.1-4(f).]
As added by P.L.1-1996, SEC.5. Amended by P.L.133-2012, SEC.102.
Structure Indiana Code
Chapter 4. Schedules for Determinations on Permits
13-15-4-1. Deadlines for Acting on Applications; Renewals
13-15-4-2. Public Hearing; Period for Ruling on Applications
13-15-4-3. Period for Ruling on Applications; Changes
13-15-4-4. Review of Permit Renewal
13-15-4-5. Effect on Hazardous Waste Permit Modification Rules
13-15-4-7. Calculation of Periods
13-15-4-8. Extension of Periods
13-15-4-9. Denial of Applications
13-15-4-10. Suspension of Processing of Applications
13-15-4-12.1. Applicant Not Entitled to Refund of Application Fee for Permit Renewal
13-15-4-14. Effect of Commencement of Construction or Operation of Equipment or Facility
13-15-4-17. Notice of Applicant's Alternatives Before Expiration of Period