61-516. PRIORITY DESIGNATION FOR ELECTRIC TRANSMISSION PROJECTS. (1) The legislature finds that the timely review and permitting of electric transmission facilities is critical to the well-being of the citizens and the economy of this state and the region. The legislature further finds that enactment of this section is necessary to promote the public interest. The purpose of this section is for the public utilities commission to determine whether the construction of electric transmission facilities should be designated to receive priority processing by state agencies. This section is not intended to affect a state agency’s decision-making authority to approve, deny or condition an application to construct electric transmission facilities.
(2) For purposes of this section the following definitions shall apply:
(a) "Electric transmission facilities" means the construction of high voltage transmission lines with an operating level capacity of two hundred thirty thousand (230,000) volts or more and associated substations and switchyards.
(b) "State agency" means every state department, division, commission or board.
(3) Any person intending to construct eligible electric transmission facilities in Idaho may file an application with the public utilities commission seeking priority designation. An order granting priority designation shall not constitute regulatory approval or bind any state agency. If the commission issues an order granting priority designation, state agencies subsequently involved in the permitting or siting processes for such electric transmission facilities shall be required to give the application priority or immediate attention as it relates to reviews, permits, reports, studies or comments.
(4) In reviewing an application for priority designation, the public utilities commission shall base its findings on whether the proposed construction of electric transmission facilities will:
(a) Benefit Idaho customers and the Idaho economy;
(b) Improve electric transmission capacity and reliability in Idaho and the region; and
(c) Promote the public interest.
(5) Applications for priority designation filed with the public utilities commission shall be governed by the commission’s rules of administrative procedure. The commission may promulgate administrative rules in compliance with chapter 52, title 67, Idaho Code, or may issue procedural orders necessary to implement this section.
History:
[61-516, added 2009, ch. 9, sec. 1, p. 11.]
Structure Idaho Code
Title 61 - PUBLIC UTILITY REGULATION
Chapter 5 - POWERS AND DUTIES OF PUBLIC UTILITIES COMMISSION
Section 61-501 - INVESTMENT OF AUTHORITY.
Section 61-502 - DETERMINATION OF RATES.
Section 61-502A - RESTRICTION ON RATES AUTHORIZING RETURN ON PROPERTY NOT PROVIDING UTILITY SERVICE.
Section 61-502B - ALLOCATION OF GAIN UPON SALE OF WATER RIGHT.
Section 61-503 - POWER TO INVESTIGATE AND FIX RATES AND REGULATIONS.
Section 61-504 - ESTABLISHMENT OF THROUGH ROUTE AND JOINT RATE.
Section 61-506 - INTERSTATE RATES.
Section 61-507 - DETERMINATION OF RULES AND REGULATIONS.
Section 61-508 - IMPROVEMENTS MAY BE ORDERED — COST.
Section 61-509 - REGULATION OF TRAIN AND STREET CAR SERVICE.
Section 61-510 - RAILROAD SERVICE — PHYSICAL CONNECTIONS.
Section 61-511 - RAILROAD SERVICE — SPURS AND SWITCH CONNECTIONS.
Section 61-512 - RAILROAD SERVICE — CARS OF CONNECTING RAILROAD.
Section 61-513 - TELEPHONE COMPANIES — PHYSICAL CONNECTIONS.
Section 61-514 - JOINT USE OF PLANT AND EQUIPMENT.
Section 61-515 - SAFETY REGULATIONS.
Section 61-515A - SAFETY AND SANITARY EQUIPMENT AND CONDITIONS.
Section 61-516 - PRIORITY DESIGNATION FOR ELECTRIC TRANSMISSION PROJECTS.
Section 61-518 - RAILROAD SERVICE — FURNISHING CARS.
Section 61-519 - EXPRESS SERVICE — DELIVERY OF TELEPHONE MESSAGES.
Section 61-520 - SERVICE OF ELECTRIC, GAS, AND WATER CORPORATIONS — DETERMINATION OF STANDARDS.
Section 61-521 - AUTHORITY TO ENTER PREMISES.
Section 61-522 - CONSUMER MAY HAVE COMMODITY OR APPLIANCE TESTED.
Section 61-524 - SYSTEM OF ACCOUNTS.
Section 61-525 - DEPRECIATION ACCOUNT.
Section 61-526 - CERTIFICATE OF CONVENIENCE AND NECESSITY.
Section 61-527 - CERTIFICATE OF CONVENIENCE AND NECESSITY — EXERCISE OF RIGHT OR FRANCHISE.
Section 61-528 - CERTIFICATE OF CONVENIENCE AND NECESSITY — CONDITIONS.
Section 61-531 - PLAN FOR CURTAILMENT OF ELECTRIC OR GAS CONSUMPTION.
Section 61-532 - ADOPTION OR REJECTION OF PLANS — PROCEDURE.
Section 61-533 - AUTHORITY TO DECLARE EMERGENCY.
Section 61-534 - CURTAILMENT OF SERVICE BY SUPPLIERS IN ACCORDANCE WITH PLANS.
Section 61-535 - ORDER FOR CURTAILMENT OF CONSUMPTION BY CONSUMERS.
Section 61-536 - LIABILITY OF SUPPLIERS.
Section 61-537 - CONTRACTS OF SUPPLIERS SUBJECT TO PROVISIONS OF LAW.
Section 61-538 - POLE ATTACHMENTS — REGULATION.
Section 61-539 - WATER RIGHTS OF AN ELECTRICAL CORPORATION — NO COMMISSION JURISDICTION.