§ 13-10-40. Large Public Works Contracts; Requirement for Performance Bond

Except as otherwise provided in Title 32, performance bonds shall be required for all state public works construction contracts with an estimated contract amount greater than $100,000.00; provided, however, that the state may require a performance bond for public works construction contracts that are estimated at $100,000.00 or less. No public works construction contract requiring a performance bond shall be valid for any purpose unless the contractor gives such performance bond. The performance bond shall be in the amount of at least the total amount payable by the terms of the contract and shall be increased as the contract amount is increased.
History. Code 1981, § 13-10-40 , enacted by Ga. L. 2001, p. 820, § 1.
Editor’s notes.
For application of this statute in 2020, see Executive Orders 06.11.20.01, 06.29.20.02, 07.15.20.01, 07.31.20.02, 08.15.20.01, and 08.31.20.02.
A listing of Executive Orders issued in 2020 and 2021 can be found at https://gov.georgia.gov/executive-action/executive-orders.
Law reviews.
For article, “A Georgia Practitioner’s Guide to Construction Performance Bond Claims,” see 60 Mercer L. Rev. 509 (2010).